What order should a business site electrify in?

Measure first, cut waste second, then add heat and vehicles in stages against one capacity budget.

  1. Measure maximum demand. The Energy Networks Association (ENA) says the first step is to confirm how much electricity the site already uses and when, and that the two simplest ways to find maximum demand are a smart meter or asking your energy supplier.
  2. Cut waste. ENA notes that a site able to reduce the power used for machinery, heating or lighting could save a significant amount rather than paying for more network capacity.
  3. Add heat and vehicles as plant and fleet come up for replacement, not all at once, so each step is sized against measured demand. The solar and heat pump guide shows where on-site generation fits.
  4. Check the funding lines. The Boiler Upgrade Scheme sets a maximum of 45kWth for individual systems, and gov.uk says the Workplace Charging Scheme rate rose to £500 per socket on 1 April 2026.

How much capacity does each addition need?

For chargers, the Energy Saving Trust's fleet toolkit sets out the supply each charge point needs.

Charge point, per outletNew supply capacity needed now
Fast 7kW ACGenerally not required
Fast 11kW ACThree-phase supply, 16A per phase
Fast 22kW ACThree-phase supply, 32A per phase
Rapid 50kW DCThree-phase supply, 100A per phase

The toolkit adds that most lower-powered charge points can use a building's existing connection, while higher-powered ones may need new connections or upgrades. It also notes that SSEN treats connections up to 70 kVA as small, 70 to 200 kVA as medium and over 200 kVA as large, and that large connections can bring transformer management and network reinforcement. A site with only a single-phase supply can check what it has, and how an upgrade works, in the three-phase supply guide.

A heat pump's electrical load is its heat output divided by its coefficient of performance (COP). For example, a heat pump delivering 90 kW of heat at a COP of 3 draws about 30 kW of electricity, and a resistance electric boiler draws close to its full heat output. The heat pump guide explains COP.

A hypothetical illustration, treating kW and kVA as equal for simplicity: a unit with a 200 kVA capacity that peaks at 140 kVA has about 60 kVA of headroom. Adding four 22 kW chargers (88 kW) and a 30 kW heat pump (118 kW in all) could take the peak to roughly 258 kVA if everything ran together.

Load management that holds the chargers to the headroom left after the building and heat pump, about 30 kVA, keeps the site inside its capacity at the cost of slower charging at busy times.

How do you check the supply you already have?

Half-hourly sites have a Maximum Import Capacity (MIC) in kVA. Electricity North West (ENWL) says kVA is a measurement of apparent power, that many MICs are legacy values from when the site was first connected, and that the supplier's bill shows how much kVA you use each month. Chargers and heat pumps are rated in kW, and kVA is at least as large, so the power factor guide helps when comparing the two. The kVA to kW calculator does the conversion for a given power factor.

  • Read the connection agreement and your supplier's bill for the MIC and monthly kVA.
  • Check the smart meter or ask the supplier for maximum demand.
  • Contact your operator, found with the network operator guide. ENA says local network assets cannot be assessed without contacting the operator, even when the cut-out rating is known.

Getting it wrong costs money. ENWL says you could be charged up to twice as much if you use more than your allocated capacity, recommends setting the MIC 10% above the last 12 months' peak, and says the MIC can be changed only once in each 12-month period. Reducing it carries no charge, but increasing it could need network reinforcement.

Can load management avoid a supply upgrade?

Often it can defer one. ENA's fleet guidance lists the options:

  • Load management controls the power to chargers so the site stays under its supply limit; chargers still run together, at a slower rate.
  • Timed profile connections agree with the operator that charging happens only at set times.
  • Smart charging or flexible connections can be granted where the connection is constrained.
  • On-site generation and battery storage can supply charging so less comes from the network.

The battery savings guide explains how a battery can cover short peaks, and the solutions overview shows how heat, vehicles, solar and storage fit together. Only half-hourly data and the operator's reply can say whether deferral works for your site.

How do you ask the network operator for more capacity?

  1. Work out the kVA you need. SSEN says a commercial application must state the required kVA, which an electrician or its demand calculator can confirm.
  2. Apply. SSEN asks for a site plan, your current and required amount of electricity and project details; ENWL takes applications for additional load to an existing supply.
  3. Receive a design and quote. ENA says the operator quotes for works from the substation to your meter cabinet. SSEN says a quote is valid for 90 days.
  4. Pay, then plan the work. SSEN says work starts once payment is received and all required legal land rights and council permits are approved, and it lists customer tasks such as fitting meter boards, laying ducting and booking the supplier to update the meter.

For smaller heat pump and charge point installations, ENA says its Connect Direct platform offers an almost instant approval mechanism; larger commercial loads go to the operator's connections team as above. Electricity North West's business guidance also suggests identifying the critical functions that rely on electricity, which matters more once heat depends on the supply.

Timing depends on reinforcement, land rights and permits, so start the application before ordering equipment. An all-electric site also depends more heavily on its supply, so read the backup power guide alongside the plan. To compare options for your own site, you can send an enquiry through the form on this page.

Sources and last checked

Guides on this topic

Common questions

How do I know if my supply can take a heat pump?

Compare the heat pump's electrical input with the headroom between your maximum demand and your Maximum Import Capacity. ENA says you may need to contact your network operator before a low-carbon technology is installed, because local network assets cannot be assessed without the operator.

What is the difference between kW and kVA?

kW is real power, which is how heat pumps and chargers are usually rated. ENWL describes kVA as apparent power, and half-hourly supplies are agreed in kVA, so convert using the power factor before comparing.

Does every EV charger need a supply upgrade?

No. The Energy Saving Trust's toolkit says new supply capacity is generally not required for a fast 7kW AC charge point, while 22kW AC units need a three-phase supply at 32A per phase and rapid 50kW DC units 100A per phase. Load management can reduce what the site needs.

Can I reduce capacity I no longer use?

Yes. ENWL says there is no charge for reducing a Maximum Import Capacity, but the MIC can be changed only once in each 12-month period and increasing it later could need reinforcement. Check your seasonal peaks before reducing.