Flexible Grid Connections: Connecting Sooner in Exchange for Curtailment
Updated 10 November 2026 · Renewable Energy for Businesses
Need to know what your grid connection can take?
Request a quoteWhat is the difference between a firm and a flexible connection?
A firm connection gives a site its agreed capacity whenever it needs it, faults aside. A flexible, or non-firm, connection gives up some of that certainty in exchange for connecting sooner or for less. Electricity North West (ENWL) describes it as a connection whose import or export capacity is restricted under certain conditions, such as faults or network stress, and says it is optional, can be temporary or permanent, and can bring an earlier energisation date or a cheaper quote where it avoids or defers reinforcement.
Ofgem's Access and Forward-Looking Charges decision of 3 May 2022 set out to make a standardised non-firm option available to larger network users, with clear curtailment limits and end dates. The industry code change that delivers it, DCP404, standardises and clarifies access rights for non-firm connections to the distribution network, and Ofgem approved it to apply from 1 April 2023.
Which kinds of flexible connection do network operators offer?
Each operator names its products differently, so ask for any offer to be described in these terms. The table uses the operators' own names.
| Type, as the operator names it | How curtailment happens | Typical business use | What to ask |
|---|---|---|---|
| Timed Connection (ENWL); Profiled Connection (UK Power Networks) | Capacity is available only at agreed times, or import is held to a fixed profile. UK Power Networks offers its Profiled Connection for import constraints only, in place of the older Timed Connection. | Loads that can run off-peak; ENWL's example is a site that only needs power overnight | Which hours or profile apply, and whether they change by season |
| Import Limited Connection (ENWL) | The site can install more demand than its agreed capacity, but its import from the network is capped | A site that can hold its peak down with load control or storage | How the cap is enforced and what happens if it is breached |
| Export Limited Connection (ENWL) | More generation can be installed than may be exported, and export is capped at an agreed level | On-site generation that mostly serves the site's own demand | The export cap and the limiting equipment required |
| Active Network Management, or ANM (ENWL, NGED); Flexible Connection (Thermal) (UK Power Networks) | A control system adjusts import or export in real time to the capacity available; UK Power Networks sends upper set points to the site | Larger sites: NGED says sites as small as 500 kW on its 11 kV network can use ANM | The site's place in the curtailment order; NGED uses Last In, First Out |
| Transmission-driven curtailment: technical limits (ENWL, UK Power Networks); Transmission ANM (NGED) | Output or demand is limited because the transmission network, not the local one, is short of capacity | Mainly generation and storage waiting for transmission works | Whether this curtailment counts towards the curtailment limit |
The last question matters. Ofgem's DCP404 decision explains that the code's definition of curtailment excludes distribution network actions resulting from constraints on the transmission network. UK Power Networks also separates interim curtailment, which lasts until distribution reinforcement is completed, from enduring curtailment, which applies to sites without an end date and to sites connected before the reforms.
What rules have applied to curtailable offers since April 2023?
Ofgem's DCP404 decision, published on 15 December 2022, sets out the standard terms. In short:
- When an offer is made: only where the operator has identified a need for reinforcement to make the connection. SSEN adds two conditions: the reinforcement must not be only for fault level or reactive power issues, and a curtailable connection must be possible before the reinforcement is finished.
- Who can have one: not small users. SSEN defines them as customers billed on an aggregated, non-site-specific basis or metered directly through whole-current meters, plus unmetered supplies; ENWL puts whole-current metering at up to 20 kVA single-phase and 60 kVA three-phase. In practice, that means current transformer (CT) metered sites.
- What comes with the offer: information on the expected costs of the firm, non-curtailable alternative, so the customer can make an informed decision.
- The limit: a curtailment limit, which ENWL expresses in hours a year, for example 4,000 of the 8,760 hours.
- Above the limit: the operator pays the customer at a set price. Ofgem's direction says the price must be markedly higher than contracted prices for flexibility and consistent across operators, and operators must use reasonable endeavours to stay within agreed limits.
- The end date: agreed between the customer and the operator, and movable only in limited circumstances with sufficient notice.
Practice differs at the edges. SSEN's page says that from 1 June 2023 it would automatically offer curtailable connections to new applications needing more than 10 MW of export or 10 MVA of import, and that customers can ask for one on the application form. ENWL makes a curtailed offer only with a formal connection offer, not with a budget estimate.
How much curtailment should a business plan for?
Get the operator's estimate in writing and test the site against it. UK Power Networks says it has issued curtailment assessment reports at offer stage since it began offering flexible connections in 2019, and runs a Connections Lab app showing potential curtailment and the connection queue at each grid supply point. ENWL gives flexible connection customers a curtailment forecast and index, then reviews actual curtailment with them each year once connected.
Read any estimate as a product of the area, not just the site. Ofgem's DCP404 decision describes the limit as built from the annual load profile of the asset that needs reinforcing, plus accepted offers, issued offers and new connections, adjusted for how likely they are to go ahead. Then plan to live within it:
- Move flexible loads, such as vehicle charging or batch processes, into the hours the network leaves open; the guide to electrifying a business site covers load management.
- Cover curtailed hours with stored or on-site energy; the battery savings guide sets out what storage earns.
- Check whether the same flexibility could be paid for when the network is not constrained, as the demand side response guide explains.
A site that wants these options compared against a firm connection can send its capacity need and timing through the enquiry form.
Does a flexible connection work differently for demand and for generation?
For new demand, the constraint is usually how much power the local network can deliver at its peak. UK Power Networks says flexible connections are available for demand as well as generation, provided the asset can be flexed under real-time control from its remote terminal unit. A business accepting one therefore needs loads it can turn down on instruction without stopping the work that pays for the connection.
For generation and storage, the bottleneck is more often the transmission network. ENWL says generation of 1 MW or more needs transmission consent from National Grid, and that most delays to connection dates come from transmission works rather than its own network. G99, the requirements for connecting generation to the distribution network, applies to generation over 16 amps per phase, ENWL notes.
What should a business ask the network operator before accepting?
Screen the area first with the operator's maps, as the guide to DNO heat maps and demand capacity explains, and follow the application steps in the guide to a new business electricity connection. The MPAN guide shows how to identify the operator from a bill. When an offer arrives, ask:
- Is the curtailment driven by a distribution constraint, a transmission constraint or both, and which part counts towards the limit?
- What is the curtailment limit in hours a year, and what price is paid for curtailment above it?
- What is the end date, what could move it, and does the connection become firm once reinforcement is complete?
- What would the firm alternative cost, and when could it be delivered?
- What control equipment and communications are needed? NGED says every extra-high voltage connection needs a Connection Control Panel at the boundary, and put the communications and circuit breaker needed to police an ANM set point at around £32,000 (typical cost in September 2020), adding that they are not required as standard below 33 kV.
- Where does the site sit in the curtailment order, and could later connections change that?
- How will curtailment be measured and reported to the site, and how often?
Once the answers are in, a business ready to compare options can send the site's capacity need through the quote form.
Sources
All pages checked 10 November 2026.
- Ofgem: Decision on DCP404 (15 December 2022) and its decision document; Access SCR decision and direction (3 May 2022).
- SSEN: Access SCR.
- UK Power Networks DSO: Curtailment and DERMS.
- Electricity North West: Flexible connections; Curtailed Connection Offers; Curtailment information; Releasing capacity and enabling connections; Generation G99.
- National Grid Electricity Distribution: Active Network Management (ANM).
Common questions
Can a small business get a curtailable connection?
Usually not. Curtailable offers under the April 2023 rules are not available to small users, which SSEN describes as customers on whole-current meters or billed on an aggregated basis. ENWL puts whole-current metering at up to 20 kVA single-phase and 60 kVA three-phase, so the offers are aimed at larger, CT-metered sites.
Does a curtailable connection stay curtailable for ever?
Not if it has an end date. Since April 2023 the operator and customer agree an end date after which the right to curtail may cease, and it can move only in limited circumstances. Connections without an end date, and those agreed before the reforms, can face enduring curtailment.
Is a flexible connection the same as demand side response?
No. A flexible connection is a condition of connecting: the operator can limit the site at certain times. Demand side response is a separate, paid service in which a site chooses to change its use when asked, although the same flexible loads can sometimes do both.
Will the operator pay if it curtails more than agreed?
Under the DCP404 rules, yes, for curtailment above the agreed limit. The operator pays at a set price that Ofgem's direction says must be markedly higher than contracted prices for flexibility. Curtailment caused by transmission constraints sits outside the code's definition, so ask how it is treated.