Getting a New Business Electricity Connection: Process, Costs and Timescales
Updated 28 October 2026 · Renewable Energy for Businesses
Need to know what your grid connection can take?
Request a quoteWho do you apply to for a new business electricity supply?
The company that owns the local wires, not the one that sells you energy. Usually that is the distribution network operator (DNO) for the area, and the guide to finding your DNO shows how to identify it.
Some business parks and newer developments are on an independent distribution network operator (IDNO) instead, which National Grid Electricity Distribution (NGED) describes as a company licensed by Ofgem to own and operate electricity networks. Requests there go to the IDNO, and the guide to IDNOs explains how to tell.
Generation and storage projects also face a reformed connection queue in which, Ofgem says, projects that are ready and needed get Gate 2 offers; this guide covers demand.
What does a connection application need?
The legal clock for a quotation starts only once the operator has the information it reasonably needs, so send a complete pack. NGED and Scottish and Southern Electricity Networks (SSEN) ask for:
- Capacity and dates: the type and size of connection, how much electricity you expect to use, and when you will be ready for the works. For a load increase on its largest projects, SSEN says you must state the total capacity required after the increase.
- Loads: abnormal loads such as heat pumps, any small generation such as solar panels, specification sheets for electric boilers or similar equipment, and an ENA EV/HP form where chargers or heat pumps are planned.
- Plans: a site location plan and a site layout plan showing the proposed meter position.
- Land: where your ownership ends, because the connection may need land consent, and a letter of authority if someone applies for the landowner, tenant or occupier.
SSEN charges large projects connection offer expenses under the Electricity (Connection Offer Expenses) Regulations 2018, payable whether or not you accept the quotation, and from 1 June 2026 asks demand projects of 5 MVA or more for a single line diagram. The guide to electrifying a business site helps with the capacity figure, and you can send the details as an enquiry through the quote form.
What are the steps from application to switch-on?
- Budget estimate (optional). A written figure that may be given without a site visit or system studies, stating its assumptions and whether associated works such as reinforcement are likely.
- Quotation. Note which tasks it gives to you and which it lists as prerequisites, because those decide whether dates can move later.
- Acceptance and payment. Accept in writing inside the timescale the quotation specifies and pay what is due, plus any reasonable security. The operator must then contact you to agree dates for starting, completing and energising.
- Land rights. SSEN says it needs land rights to install, use, maintain and renew its equipment on privately owned land. For substation sites on schemes built by an independent provider, Electricity North West asks the owner to transfer a small parcel of land by freehold or long leasehold.
- Works. SSEN lists design changes, site readiness, material lead times, third parties and land rights among the things that can delay a connection.
- Meter and energisation. NGED says you must choose a supplier before it can begin work, and the supplier uses the MPAN the operator provides to fit the new meter; a larger three-phase supply generally gets a CT meter (current transformer meter). Energisation is the fuse or switch operation that lets current flow to your installation.
Can an independent connection provider build it instead?
Often, for part of it. NGED splits the work into contestable elements, which an ICP or IDNO can undertake, and non-contestable elements, which NGED or its appointed agents must complete. Ofgem's rules for DNOs from 30 October 2015 aimed to give businesses real choice here.
| Contestable: NGED, an ICP or an IDNO | Non-contestable: NGED only |
|---|---|
| Design of extension assets, the new assets serving the site | Design of upstream reinforcement |
| Trenching, ducts, cable laying and on-site substation civil works | Wayleave and easement documents with third-party landowners |
| Negotiating land rights with third-party landowners | Operations, repairs and maintenance afterwards |
| Live connection of the new works at low voltage | Connection at high or extra-high voltage, and commissioning |
LRQA operates the National Electricity Registration Scheme (NERS) on behalf of the UK DNOs, and says an accredited provider is commonly known as an Independent Connection Provider (ICP). NGED's page still names Lloyd's Register EMEA and says an ICP must hold the relevant scopes for the work, so check them on LRQA's register first.
Two limits matter. NGED says contestable works done for an ICP or IDNO are not covered by its connection standards, so set the ICP's programme in your contract. And Electricity North West will not adopt equipment installed by an ICP or IDNO until the land rights have been legally secured.
How long can the network operator take, and what if it is late?
The Electricity (Connection Standards of Performance) Regulations 2015 set deadlines for each stage in Great Britain. They cover upgrades too, because a demand connection means a new or modified connection.
The timetable follows voltage. Low voltage means up to 1,000 volts and high voltage more than that, up to 22,000 volts, judged by the highest voltage of the assets involved, including associated works such as reinforcement. So a low-voltage business supply can fall into the high-voltage timetable if the network behind it needs high-voltage work. A single premises needing a two-phase or three-phase connection with only a service line and fuses, fused at 100 amperes or less per phase, has a shorter one.
| Stage | Deadline | Schedule 1 base payment if missed |
|---|---|---|
| Budget estimate | 10 working days below 1 MVA; 20 working days at 1 MVA or more | £75, once |
| Quotation: single premises, two- or three-phase, service line and fuses only | 15 working days | £20 per working day late |
| Quotation: other low voltage | 25 working days | £75 per working day late |
| Quotation: high voltage | 35 working days | £160 per working day late |
| Quotation: extra-high voltage | 65 working days | £235 per working day late |
| Contact to agree dates after acceptance and payment (LV / HV / EHV) | 7 / 10 / 15 working days | £75 / £160 / £235 per working day late |
| Start the works | The agreed date | £30 per working day late |
| Complete the works (LV / HV / EHV) | The agreed date | £160 / £235 / £315 per working day late |
| Energise the connection (LV / HV / EHV) | The agreed date | £160 / £235 / £315 per working day late |
These base sums come from the Schedule 1 table substituted on 1 October 2023. Regulation 17A adjusts them for each financial year from 1 April 2024 in line with CPIH against January 2023, rounded to the nearest £5, and each operator must keep its current statement of these rights on its website.
NGED says connection payments are automatic. Agreed dates are extended for severe weather, street works permits, delays with consents, rights or land, and unfinished prerequisite works that are not the operator's responsibility, which can include your own site works. An extension only takes effect if the operator tells you.
How are connection charges worked out?
Each operator prices to its own connection charging methodology. NGED says each application is individually assessed, and for a single commercial property lists the factors: the surface to be dug up and reinstated, the distance from the existing mains, the number of connections, legal permissions and consents, and traffic management. Where capacity is short, it may need to upgrade equipment or install a new transformer.
Reinforcement charging changed in 2023. Ofgem's decision of 3 May 2022 set out to reduce the overall connection charge faced by those connecting to the distribution network. NGED says that for applications from 1 April 2023, demand customers no longer pay a proportion of upstream reinforcement costs, while all customers still pay for the extension assets that provide their new connection.
NGED and SSEN name the exceptions: a demand project that triggers the high-cost project threshold, which both give as £1,720/kVA, or a speculative development, with SSEN adding temporary supplies. Both treat energy storage as generation for connection charging.
Where reinforcement is needed, SSEN says a curtailable connection may let a site connect quicker by accepting restricted use at certain times. Where several applications use the same parts of the network, quotations can become interactive, so the validity of one depends on the outcome of another. To compare options for a heat pump, charger or solar project, you can send the site details through the enquiry form.
Sources
All pages were checked on 28 October 2026.
- legislation.gov.uk: Electricity (Connection Standards of Performance) Regulations 2015, regulations 2, 4, 5, 6, 9, 16, 17A and 18, and Schedule 1 (table substituted 1 October 2023).
- Ofgem: Access SCR decision (3 May 2022); competition in connections (28 October 2015); Moving to a reformed grid (8 December 2025).
- NGED: information for customers; new to connections; single commercial property; connection standards; significant code review.
- SSEN: large new connections; Access SCR. Electricity North West: land rights for ICPs. LRQA: NERS.
Guides on this topic
- DNO Heat Maps and Network Capacity: Checking Headroom Before a Site Adds Load
- Flexible Grid Connections: Connecting Sooner in Exchange for Curtailment
Common questions
Can my energy supplier arrange the new connection for me?
No. The network operator, or an ICP you appoint, builds the connection, and the supplier fits the meter at the end using the MPAN the operator provides.
Is a capacity increase treated like a new connection?
Yes, for the legal deadlines, because the 2015 regulations define a demand connection as a new or modified connection. State the total capacity you need after the increase, not only the extra.
When does the quotation deadline start counting?
When the operator has the information it reasonably needs that you could be expected to know, plus any connection offer expenses it may charge. Missing plans or load figures delay the start.
Do I have to use an independent connection provider?
No. NGED says it can provide a complete connection service, and that you may also ask an ICP to do some of the works. If you use one, check its NERS scopes and agree its programme in the contract.