DNO Heat Maps and Network Capacity: Checking Headroom Before a Site Adds Load

Updated 10 November 2026 · Renewable Energy for Businesses

Need to know what your grid connection can take?

Request a quote

Is there room for more demand, and at which substation?

Demand headroom and generation headroom are different numbers, even at the same substation. Demand is limited by how much power the equipment can deliver when local use peaks; generation by how much it can take away when local use is low, which is why Northern Powergrid says minimum demand can be particularly important when connecting generation. A map can show room to export and little room to import, or the reverse.

Demand capacity is also measured against a security standard. Electricity North West's heatmap tool gives separate figures for "Demand Firm", a connection whose supply stays secure if a single circuit is lost, and "Demand N-0", one that is constrained off when the first circuit is lost until it is restored. A business that cannot stop when a circuit fails should read the firm figure.

The size of the new load decides which part of the network matters. ENWL's user guide gives the typical size of a single connection at each voltage level and describes what feeds it:

Voltage levelTypical single connection (ENWL)What feeds that voltage (ENWL)
132 kVAbove 40 MWGrid supply points, the interface with the 400 kV or 275 kV transmission network
33 kV7 MW to 40 MWBulk supply points, typically two 132/33 kV transformers feeding several primary substations
11 kV or 6.6 kV0.2 MW to 7 MWPrimary substations, typically two 33/11 kV or 33/6.6 kV transformers feeding a radial high voltage network
Low voltageBelow 0.2 MWLocal distribution substations

Most business supply increases sit in the bottom two rows, so the primary substation and the bulk supply point above it are where to look first. ENWL notes that the spare capacity it quotes for a primary substation already takes account of constraints at the associated bulk supply point.

Where does each operator publish its demand capacity data?

Tools are renamed and replaced, so the table uses each operator's own wording as checked on 10 November 2026.

OperatorMap or datasetWhat it shows for demand
UK Power NetworksOpen Data Portal: Network Operational Data Dashboards and the Large Demand DashboardKey characteristics and data for grid, primary and secondary substations, and insights on large demand sites and accepted projects; registration is needed to view the datasets
National Grid Electricity Distribution (NGED)Network Opportunity & Development MapDemand and generation headroom at bulk supply points and primary substations, for the existing connected position and the future contracted position, plus an indication of demand at distribution substations
Scottish and Southern Electricity Networks (SSEN)Generation Availability and Contracted demand map; Network Rating and Loading dataAn indication of the network's capability to connect large developments to major substations, and loading and maximum demand data for feeders and substations
SP Electricity North WestHeatmap tool, as an Excel workbook and an interactive mapEstimated spare capacity at primary substations and bulk supply points by connection type; the download in use on 10 November was dated 22 October 2026
Northern PowergridDemand heat mapsA high-level indication of capability to connect more demand, updated monthly
SP Energy NetworksCapacity Heatmaps Information Model, one dataset each for SP Distribution and SP Manweb, on its Open Data PortalCapacity, utilisation and constraint status of substations on its 11 kV and 33 kV networks, including demand and generation firm and available capacities
NIE Networks (Northern Ireland)Network Capacity MapDemand, generation and fault level capacity at primary substation level; map data last updated 30 October 2026

How much can a green substation be relied on?

As a first screen, a great deal; as a promise, not at all. The colour rates spare capacity at a point in time against thresholds each operator sets for itself. NIE Networks, for example, calculates capacity with load flow tools and marks a primary substation red at 0 MVA of demand capacity, amber above 0 and up to 1 MVA, and green above 1 MVA, colouring each pin by the worst case across the primary substation, the 33 kV circuits feeding it and the bulk supply point. NGED says its colour gradings point users to areas where a connection is more likely without significant distribution reinforcement.

Before relying on a rating, check what sits behind it:

  • A total, not a per-site allowance. ENWL says its spare capacity figures are the total available to connections, not the largest single connection, which can be significantly less.
  • Constraints left out. ENWL's tool excludes 132 kV network constraints and the effect of meshed networks, where substations share circuits.
  • Capacity already promised. NGED shows a future contracted position next to the existing connected one; read both.
  • The last few hundred metres. Most maps stop at primary substations, as ENWL's tool and NIE Networks' map do; NGED and UK Power Networks publish some data for smaller distribution or secondary substations.
  • Accuracy. ENWL says its tool cannot replicate the accuracy of the detailed assessment in the formal application process, and NIE Networks says its map cannot be relied on to assess the terms of connection for specific premises.

What planning data sits behind the maps?

Three published sources explain why headroom looks as it does and how it may change.

Long Term Development Statement (LTDS). Northern Powergrid compiles its statement under standard condition 25 of the electricity distribution licence, publishes it before the end of November each year with an interim update before the end of May, and says it gives developers enough information for initial assessments of system capability. UK Power Networks says its LTDS covers a 0 to 5 year period.

Network Development Plan (NDP). UK Power Networks says its plan looks ahead 10 years. NGED's map carries an NDP layer showing constraints and solutions at each grid supply point, bulk supply point and primary substation for the next 10 years, through flexibility services, conventional reinforcement or operational mitigation.

Distribution Future Energy Scenarios (DFES). Operators also publish scenarios for how their areas could develop; UK Power Networks, for example, publishes its latest DFES aggregated by local authority district on its Open Data Portal.

The data itself may become more consistent. Ofgem's consultation on transforming connections data, published on 25 September 2026, proposed new datasets including a demand capacity register; it closed on 7 November and was awaiting a decision when checked, with Ofgem planning to roll out new requirements in early 2027. Treat it as a proposal until Ofgem decides.

How should a business use the maps before applying?

  1. Find the operator. The distributor ID at the start of the MPAN's 13-digit core names it, and the MPAN guide shows where it sits on a bill. A unit on an independent network deals with that operator instead, as the guide to IDNOs explains.
  2. Size the change. Work out the total capacity the site will need after the new load is added, in kVA.
  3. Locate the substations. Find the primary substation feeding the site and the bulk supply point above it. Northern Powergrid's LTDS even lists the postcode sectors supplied by each primary substation.
  4. Read the demand figures. Compare firm demand headroom, and the contracted position where shown, with the load you plan to add.
  5. Check what is planned. Look at the operator's NDP for reinforcement or flexibility planned near the site.
  6. Talk before applying. Ask for a budget estimate or a pre-application meeting: SSEN, for example, offers a virtual meeting to discuss a project and explore network capacity, and ENWL advises talking to it before submitting a formal application.
  7. Apply. Follow the steps in the guide to a new business electricity connection for a formal quotation.

If the headroom is not there

A thin or red substation is a reason to change the plan, not necessarily to drop it. ENWL asks customers whose site shows insufficient capacity to contact it about next steps, and says it works with customers to find solutions to network constraints, including smart technology. The usual routes are a flexible or timed connection that lets the site connect before reinforcement; load management or on-site storage that keeps the peak inside today's supply, covered in the guide to electrifying a business site; or phasing the project so the first stage fits the headroom available now. Once the capacity need and timing are clear, they can be sent with the site details through the enquiry form.

Where do generation and battery storage fit?

Adding solar, a generator or a battery turns the question from import to export, and operators publish generation headroom separately. Each operator also publishes an Embedded Capacity Register, which SSEN says gives stakeholders better information on connected resources and network requirements; Northern Powergrid keeps one register for connections of 1 MW or greater and another for 50 kW up to 999 kW. ENWL notes that G99, the requirements for connecting generation to the distribution network, applies to all generation over 16 amps per phase. A battery that imports and exports needs both figures: ENWL's tool assumes storage with matched import and export capacity, and suggests assessing unequal ones separately as demand and as generation.

Sources

All pages checked 10 November 2026. An operator's own page is the authority if it disagrees with this guide.

Common questions

Is a DNO heat map the same as a connection offer?

No. The operators describe their maps as an indication only. Electricity North West says its tool cannot match the detailed assessment made in a formal application, and NIE Networks says its map cannot be relied on for the terms of connection at a specific premises.

Why does the map show capacity for solar but not for my new load?

Because demand and generation headroom are calculated separately. A substation can have room to take exported power while having little spare capacity at its demand peak, or the other way round. Read the demand figure for any new load.

How often are the maps updated?

It varies by operator. Northern Powergrid says its heat maps are updated monthly, NIE Networks showed map data last updated on 30 October 2026, and Electricity North West's heatmap download was dated 22 October 2026. Check the date on the map before relying on it.

Does a green substation mean a connection will be cheap?

Not necessarily. NGED says green points to areas where a connection is more likely without significant distribution reinforcement, but the maps rate substations rather than a particular site, and NIE Networks says its map cannot be relied on for the terms of connection at specific premises. A budget estimate or formal quotation gives the real figure.