Power Factor Correction for Business: Are You Paying Reactive Power Charges?

Updated 23 October 2026 · Renewable Energy for Businesses

Want to cut what your site uses and pays for energy?

Request a quote

Which businesses pay reactive power charges?

The charge follows the meter. The Institution of Engineering and Technology (IET) says that where a supply is metered at half-hourly rates, which is commonly the case on commercial and industrial installations, suppliers and distribution network operators (DNOs) may charge for what they deem to be excessive reactive power use. It adds that these charges are generally applied to commercial and industrial sites where half-hourly metering is employed.

Ofgem's guide says that from 1 April 2017 all businesses in profile classes 5 to 8 were required to have their energy use recorded every half hour. The MPAN guide shows where the profile class sits on a bill, and the half-hourly settlement guide explains the wider change.

Reactive power does no direct work, says the IET, which names motors without any power factor correction as a frequent cause of poor power factor. CIBSE Journal adds that many motors driving fans, pumps and compressors need extra current to produce a magnetic field.

What do 0.95 and the 33 per cent rule mean?

CIBSE Journal defines power factor as the ratio of real power (kW) to total, or apparent, power (kVA). The IET adds that a system at 1 would consume only active power, and that anywhere between 0 and 1 the system consumes a mix of active and reactive power.

The IET calls one methodology common: reactive charges apply where the power factor averages below 0.95 for a half-hour period, and they are charged on any units of kVArh exceeding 33 per cent of the kWh used. The two figures describe the same line, because 0.33 kVArh per kWh works out as a power factor of about 0.95. The table converts power factors into that ratio. It is calculated, not quoted from a charging statement.

Power factorkVArh per kWhAgainst the 0.33 line
0.980.20Below it
0.950.33On it
0.920.43Above it
0.900.48Above it
0.850.62Above it
0.800.75Above it

For example, in one half-hour a site draws 100 kWh of active energy and 45 kVArh of reactive energy. The 33 per cent line is 33 kVArh, so 12 kVArh sit above it and only those are billed. The power factor in that half-hour is about 0.91. The rate per kVArh comes from the supplier's contract and the network operator's current charging statement, and this guide quotes none.

The 0.95 figure also appears in network connection terms. UK Power Networks' connection quotation terms (version dated December 2015) set power factor at or as near to unity as practicable, but no less than 0.95. Treat 33 per cent as the common case and check the threshold in your own contract.

How do you spot reactive power charges on a bill and in half-hourly data?

  1. Find the line. Look through the bill's breakdown for a charge measured in kVArh or labelled reactive or excess reactive power. If network costs appear as a single lump, ask the supplier for an itemised breakdown.
  2. Get the data. GOV.UK says non-domestic consumers can request up to 12 months of their historic smart or advanced meter energy use data from their energy supplier. Ask for kVArh readings as well as kWh for each half-hour.
  3. Work out the ratio. For every half-hour divide kVArh by kWh. Count the intervals above 0.33 and note when they fall.
  4. Look for the pattern. The IET notes that power factor can fluctuate through the day with the loads connected, so charges may cluster around particular shifts. The monitoring guide covers what else to log.
  5. Total it. Add up a year of excess units and multiply by the rate on your bills. That is the saving available, and any quote has to beat it.

What does power factor correction equipment do?

CIBSE Journal explains that capacitors are added to a system to counteract inductive loads. They can be fixed-rating units matched to one large item of equipment, or a bank mounted close to significant loads or at the building's power intake switchgear. Centralised banks are likely to be switched in by automatic controls to match the load.

Correction mainly reduces apparent power. In CIBSE Journal's example, a 20 kW motor running at a power factor of 0.80 needs 25 kVA, and at 0.95 it needs 21 kVA, a 16 per cent fall. The module adds that this will not necessarily reduce energy bills, but may contribute to smaller cables or improved tariffs. The saving case rests mainly on the reactive charge removed.

Three cautions come up in the engineering sources:

  • Harmonics. CIBSE Journal lists computers, speed-controller inverters, electronic power supplies and discharge lighting as non-linear loads that distort the supply waveform. It warns that inappropriate balancing capacitance can add to harmonic problems, and that detuned capacitors can damp harmonics while correcting power factor. Ask any equipment supplier whether harmonics have been assessed.
  • Speed drives. Static correction must not be applied at the output of a variable speed drive, soft starter or inverter, because it will damage the electronics. The variable speed drive guide covers where drives fit.
  • Variable loads. CIBSE Journal says power factor is unlikely to be constant, with motor speed one reason, so a fixed capacitor may suit only part of the day's load.

LED lamps, covered in the LED lighting guide, are usually not a worry here, because CIBSE Journal says their power factor will normally be corrected locally within the luminaire.

Can solar PV fix poor power factor, or make it worse?

It can make it worse, which matters for a site that is adding generation. The IET explains that PV set to deliver only active power cuts the kWh drawn from the grid but leaves reactive demand unchanged, so from the supplier's side the share of reactive energy rises.

The IET's worked example shows the effect. An installation draws 100 kW and 104 kVA, a power factor of 0.96. A PV system generates 1,200 kWh over a five-day working week, so the grid supplies 2,800 kWh of active energy while the reactive energy stays at 1,143 kVArh.

Step in the IET exampleFigure
Active energy from the grid after PV2,800 kWh
Reactive energy, unchanged1,143 kVArh
Power factor seen by the supplier0.93, down from 0.96
33 per cent of 2,800 kWh924 units
Units billed (1,143 less 924)219 kVArh

The IET says PV should not be used as a remedy for poor power factor, and that the site's power factor should be measured before PV is installed. Inverters under Engineering Recommendations G98 and G99 must have a specified power factor operating range, and many modern models can supply reactive power without cutting active output if kVA headroom allows. Ask any solar designer how the inverter will be set.

How do you judge payback against your own charges?

None of the sources checked gives a typical price or payback for correction equipment, so this guide gives none. The test uses your own numbers:

  1. Total the reactive charges on the last 12 months of bills, or the excess units from the half-hourly data multiplied by the billed rate.
  2. Ask each quote to state the power factor it starts from, the target, the type of equipment, whether harmonics were assessed, and what is included.
  3. Divide the installed price by the yearly charge removed. If the charge is small or zero, there is nothing to pay back.
  4. Fit a logger after commissioning and compare like-for-like months. The charge should fall, and the data shows whether the target was reached.

Sequence matters. Motor speed, lighting and generation all change power factor, so re-measure after other planned upgrades. The voltage optimisation guide deals with supply voltage, a separate question from reactive power. Readers who want help placing power factor within a wider plan for a site can send an enquiry through the form on the energy management page.

Sources and last checked

Checked on 22 October 2026. Charging methods differ between suppliers and network operators, so your own contract and the operator's charging statement are the authority if they disagree with this page.

Guides on this topic

Common questions

Does a variable speed drive need power factor correction?

CIBSE Journal says variable voltage, variable frequency drives give near unity power factor operation for large motor loads. It also says static correction must not be applied at the output of a drive. Any correction on a site with drives needs a harmonics check first.

What power factor should a site aim for?

The IET suggests at least 0.95 as a good starting point, CIBSE Journal says buildings would typically be kept at 0.95 or above, and UK Power Networks' connection terms set 0.95 as the floor. Your own contract states the threshold that triggers a charge.

Do small business meters get reactive power charges?

The IET says reactive power charges are generally applied to commercial and industrial sites where half-hourly metering is employed. A supply without half-hourly readings has no half-hourly reactive data to charge on. Check the bill for a kVArh line before assuming either way.