How do battery, generator and UPS backup compare?

The three do different jobs, and the right choice follows the load that must stay on and the outage length the business cannot absorb, not the equipment's price.

OptionBest forRun time logicRules and upkeep
UPSServers, controls, tills and alarms that must not dropSet by the energy store inside the unit; ask for run time at your actual loadPerformance and test requirements in BS EN IEC 62040-3; ask the supplier for testing and battery replacement intervals
Battery storage, with or without solarKeeping chosen circuits live for hoursUsable kWh divided by the critical load in kWNeeds an island-capable design; grid connection and fire-safety rules apply
Diesel generatorWhole-site cover for long outagesFuel in the tank divided by burn rate, extended by refuellingPermit, oil storage, fuel duty and testing rules
HVO generatorThe same job on a different fuelSame logicSame permit and storage rules
HybridSeamless cut-over, then a long runBattery or UPS bridges; generator carries the restBoth sets of rules

Cost logic also differs. A UPS or generator is resilience spend that earns nothing until an outage, whereas a battery can also cut bills and, on some sites, earn flexibility income, so part of its cost is recovered in normal running. The savings case and the backup case should therefore be assessed together, and a site that needs many hours of cover for a few critical circuits can still end up with a generator.

When is a UPS alone enough?

BSI describes a UPS as having a primary function to ensure continuity of load power, built for loads from less than a hundred watts to several megawatts, with IT equipment a major application. A UPS alone is enough when all of these hold:

  1. The load that must stay on is small, and you know its size in kW.
  2. The unit's run time at that load covers a controlled shutdown and the cut length you are willing to accept.
  3. Nothing else on site is time-critical, such as refrigeration, heating processes, lifts or security.
  4. The business can close or work manually through a longer cut.

Compare that with the outages the system allows. Ofgem gives restoration standards of 12 hours outside severe weather, 24 hours in category 1 storms and 48 hours in category 2, and the power cut compensation guide shows what operators pay when they are missed. Electricity North West says fridge contents stay cold for 4-6 hours and freezers for 24-48 hours, which is why cold storage usually needs more than a UPS.

What should you know before relying on a battery?

Not every battery backs up a site. The government's Be Ready page says that with solar panels and a battery with power backup capability, some installations can continue to provide power during a power cut if they are designed and configured to operate independently of the grid. Ask any supplier whether the system can island, which circuits it will feed and how it behaves when the battery is low.

Run time is simple arithmetic. For example, a battery with 100 kWh of usable energy feeding a 25 kW critical load runs for about four hours, and the same battery feeding 50 kW runs for about two. The battery savings guide covers economics, connection and fire-safety rules, and the battery storage guide covers the equipment itself.

What do diesel and HVO generators involve?

  • Permits. The medium combustion plant regulations apply from 1 megawatt thermal and burn any fuel, and the Environment Agency says the permits protect air only, controlling sulphur dioxide, nitrogen oxides and dust. The specified generator controls start at 1MWth of rated thermal input, which the manufacturer can supply. A backup generator used only in an emergency is excluded from them, but at 1MWth or more it is still a medium combustion plant that needs a permit by the deadline. This guidance applies to England and Wales.
  • Testing and other uses. Testing is limited to 50 hours a year for each generator unless the regulator agrees. Using a generator for balancing services or demand side response is not emergency use, as the demand side response guide explains.
  • Fuel storage. The oil storage rules apply from 201 litres at a business, cover standby generators with a connected tank, and since May 2023 list hydrotreated vegetable oil (HVO). A bund must hold 110% of the container's capacity.
  • Fuel duty. HMRC's Excise Notice 75 lets rebated fuel generate electricity primarily for premises that are not used for commercial purposes, so a commercial site should check the notice before assuming it can use red diesel. The red diesel rules guide explains the test.
  • Siting and testing. Environment Agency guidance says to stagger tests, keep them to the minimum needed to show reliability at the appropriate load, use the electricity generated on your site, and install backup generators away from sensitive receptors, not below windows or venting onto car parks, with exhaust flues terminated vertically.
  • Grid and safety. A set that can run alongside the grid is generation, and SSEN asks for 15 days' notice before installing and commissioning generation above 50kW. Ask your operator how a standby set with a changeover switch is treated. Never run generators indoors, and keep fuel supply and maintenance schedules in place.

Switching to HVO changes the fuel, not these duties: the permit rules cover any fuel, and the storage rules name HVO. The HVO fuel guide covers what the fuel is, how it is taxed and how its carbon saving is counted.

How is a standby generator sized?

Size a standby generator from the loads it must carry, not the site's supply capacity, then convert to kVA at the set's rated power factor.

  1. List the loads that must stay on. Typically refrigeration, IT, security, pumps and working lighting. Will the set feed the whole site or only essential circuits?
  2. Add their running power in kW. Use nameplates or, better, metered demand on those circuits.
  3. Allow for starting. Atlas Copco's sizing guide puts motor and transformer inrush currents at typically six times full load current, and almost double that for today's high-efficiency motors. Sizing on starting kVA alone often oversizes a set for the running load, it warns, yet a set not sized properly can suffer large voltage and frequency dips that other loads may be more sensitive to than the motor. It also lists sequential motor starting as a factor, so ask in what order loads start.
  4. Convert kW to kVA. Atlas Copco says a standard power factor of 0.8 is assumed for most generators, so a set rated at 100 kVA delivers 80 kW of usable power. Divide your kW total by the set's rated power factor; the kVA to kW calculator works it both ways.
  5. Check the rating class and leave room. BS ISO 8528-1:2018 classifies ratings for continuous, peak-load and standby applications, which BSI says is to help understanding between manufacturer and customer, so ask which class a quoted figure uses. Add planned loads, and ask what margin the contractor allowed and why.

Hypothetical example

For example, a small cold store must keep 30 kW of refrigeration, 6 kW of lighting and 4 kW of IT running: 40 kW. Divided by a 0.8 power factor, that is 50 kVA. Treat it as the floor: the largest compressor's starting check and any planned load decide how far above 50 kVA the rating sits.

If the set will burn HVO, ask whether its rating was stated on that fuel; HVO fuel for business covers the fuel itself.

Which combination suits which business?

Many sites pair a UPS or battery to bridge the cut-over and protect IT with a generator for long outages, which matches Electricity North West's list of a UPS for essential equipment and an assessment of a backup generator.

A shop with tills and a card terminal may need only a UPS; a cold store needs generator or battery capacity sized in hours; a site with both needs the hybrid. Whichever you choose, test the whole chain together. You can send an enquiry through the form on this page to compare battery options.

Sources and last checked

Guides on this topic

Common questions

Is a UPS the same as a battery backup system?

No. BSI describes a UPS as equipment whose primary function is to ensure continuity of load power, while a battery storage system is sized in kWh to carry chosen circuits for hours. The government's Be Ready page says a battery backs up a site only if it is designed and configured to operate independently of the grid.

Can a diesel generator run on HVO?

That depends on the engine manufacturer, which should confirm the fuel is approved. The legal duties stay the same: the medium combustion plant rules cover generators burning any fuel, and the Environment Agency's oil storage guidance lists HVO among the oils it covers.

Do I need a permit for a standby generator?

Possibly. The Environment Agency says an emergency-only backup generator is excluded from specified generator controls but is still a medium combustion plant, which needs a permit if it is 1MWth or above. Use for balancing services or demand side response is not classed as emergency use.

How often can a backup generator be tested?

Guidance for England and Wales says no more than 50 hours of testing a year for each backup generator, unless the regulator agrees a higher limit in writing. Record the hours, because the record shows the exclusion criteria are met.