Three-Phase Electricity for a Business: What It Is and When You Need It
Updated 28 October 2026 · Renewable Energy for Businesses
Need to know what your grid connection can take?
Request a quoteWhat is the difference between single-phase and three-phase electricity?
A single-phase supply brings one live conductor and a neutral into the building. A three-phase supply brings three live conductors and a neutral. The three alternating currents are offset from each other, so their peaks arrive one after another rather than together, and each phase carries its own share of the load.
The voltages are set in law. Regulation 27 of the Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR) says that, unless the parties agree otherwise in writing, a low voltage supply is declared at 230 volts between the phase and neutral conductors, at a frequency of 50 hertz. UK Power Networks gives the nominal voltage at a low voltage point of supply as 230/400 volts: 230 V from any one phase to neutral, and 400 V between any two phases.
The same regulation allows the voltage to sit up to 10% above or 6% below the declared figure, and the frequency to move by 1% either way. On a 230 V supply that is a band of roughly 216 V to 253 V.
| Feature | Single-phase | Three-phase |
|---|---|---|
| Voltage | 230 V between phase and neutral | 230 V from each phase to neutral, 400 V between any two phases |
| Size of a small connection | Up to 100 A (Northern Powergrid) | Up to 69 kVA (Northern Powergrid), about 100 A on each phase |
| Typical business uses | Offices and small shops with lighting, sockets, IT and modest heating | Machinery and motors, larger EV chargers, busy commercial kitchens, larger heat pumps |
| How to recognise it | Single-phase meter; the supplier's declaration states one phase | Three-phase meter; the supplier's declaration states three phases |
| What changing involves | Usually only a larger fuse, if more current is needed (NGED offers 80 A) | Application to the network operator, work on its cable and cut-out, a new meter from the supplier, rewiring by an electrician |
How can you tell which supply your premises has?
Start with the paperwork. Under regulation 27, before a supply starts or after its characteristics change, the supplier must find out from the network operator and declare to the customer the number of phases, the frequency and the voltage. Your supplier, or the network operator for your area (the guide to finding your DNO shows which one), can tell you what is on record.
The equipment tells the same story, but look rather than touch. National Grid Electricity Distribution (NGED) explains that each low voltage customer is connected through a fused cut-out, normally inside the property or in a meter box, and that the cut-out belongs to the network operator. The operator and the meter operator can seal it, and only the network operator may replace a blown fuse, so ask a qualified electrician to confirm how many phases reach the cut-out and your distribution board.
The meter is the other clue. Electricity North West (ENWL) says an upgrade to three-phase means the supplier replacing a single-phase smart meter with a three-phase meter. Larger sites differ again: Northern Powergrid says non-domestic connections above 69kVA are normally current transformer (CT) metered, with higher ongoing costs than whole current metering, as the CT metering guide explains.
Which business equipment needs a three-phase supply?
ENWL points out that three-phase connections are no longer limited to factories running large machinery or larger commercial outlets, and that they are increasingly common in small commercial premises such as food takeaways, hair and beauty salons and newsagents. What decides it is either the total load or one piece of equipment designed for three phases.
- EV chargers. Whether a charger needs three phases depends on its power: the table in the guide to electrifying a business site shows the supply each size needs, and the business EV charging guide covers choosing chargers for staff, visitors and fleet.
- Heat pumps. A commercial unit's data sheet states whether it needs a single-phase or three-phase supply and the current it draws on each phase. That current, not the heat output, is what the network operator needs to know. The commercial heat pump guide explains how output and electrical input relate.
- Motors and workshop machinery. Check the rating plate on compressors, lathes, saws, extraction fans and welders for the phases and voltage each needs. The technical notes UK Power Networks issues with connection quotes say voltage fluctuation is generally caused by customer equipment such as motors and welders, and ask that a proposed load complies with Engineering Recommendation P28, the national standard for it. The variable speed drives guide covers efficiency rules for three-phase motors.
- Commercial kitchens. Several electric ovens, fryers and a dishwasher can together exceed one phase even when none of them is three-phase, because the loads add up at the busiest hour.
If solar panels or a battery are part of the same plan, generation has its own per-phase limit: NGED's G98 procedures cover micro-generation with an aggregate registered capacity of 16A (3.68kW) per phase or less.
How much capacity does each type of supply give?
A supply is rated by the current each phase can carry, in amps, which the cut-out fuse and the service cable limit. To turn amps into kVA, multiply by the voltage. On single-phase, kVA is 230 × amps ÷ 1,000. On three-phase, kVA is 3 × 230 × amps ÷ 1,000, which comes to the same as 1.732 × 400 × amps ÷ 1,000. The kVA to kW calculator then converts kVA to kW once you know the power factor.
| Current per phase | Single-phase capacity | Three-phase capacity |
|---|---|---|
| 60 A | About 13.8 kVA | About 41.4 kVA |
| 80 A | About 18.4 kVA | About 55.2 kVA |
| 100 A | About 23 kVA | About 69 kVA |
Published sizes line up with this arithmetic. Northern Powergrid's small connections cover single-phase up to 100A or three-phase up to 69kVA, which is 100 A on each phase. ENWL says the standard domestic supply, up to 20kW, is single-phase, and that a supply above 20kW may need an amp increase or a move to three-phase. ENWL describes its standard three-phase connection as 60kVA, distributing 80 amps per phase; the arithmetic at 230 V gives about 55 kVA for 80 A, so plan around the capacity in your own connection offer.
What does phase balance mean in practice?
Think of a three-phase supply as three 230 V supplies sharing a neutral, each with its own current limit. Three-phase equipment such as a motor draws roughly the same current from all three. Single-phase loads, such as socket circuits, lighting, a single-phase charger or a water boiler, are each connected to one phase at the distribution board, and the electrician decides which.
Because the limit applies per phase, an unevenly loaded board runs out of room early. For example, on a 100 A per phase supply carrying 95 A on one phase and 25 A on each of the other two, a new 20 A single-phase load will not fit on the busy phase, even though the site is using less than half of its 300 A in total. Moving circuits between phases, or choosing three-phase versions of large equipment, recovers that headroom.
Balance matters to the network too. UK Power Networks names Engineering Recommendation P29 as the national industry standard for voltage unbalance, and warns that equipment distorting the voltage waveform can disturb other users or damage connected apparatus, in which case it may suspend the supply. Before adding a large load, ask your electrician to record the current on each phase at the busiest time of day.
How does a business get a three-phase supply?
The network operator for the area makes the change, not your energy supplier. NGED, for example, takes applications to increase the capacity of a domestic or small commercial connection, including upgrading from single-phase to multiple phases. The usual steps:
- Size the load. List the equipment you plan to add with the current per phase from each data sheet, and have an electrician compare it with readings from your board.
- Apply to the operator. Northern Powergrid's application asks for the date by which the connection is needed, a site location plan with the boundary and proposed meter positions marked, and a letter of authority if someone applies on behalf of the owner or occupier.
- Get the cost. NGED says the cost depends on the specifics of the application and is worked out under its Connections Charging Methodology, and it offers a self-serve budget estimate tool for indicative prices.
- Split the work. NGED's commercial connection notes describe the operator installing the equipment from its network to your meter position and excavating public highways. You may dig on your own land if you wish, your builder installs the meter cabinet, your supplier charges for fitting the new meter, and a qualified electrician must do the internal wiring.
- Change the meter. Tell your supplier early. ENWL warns that swapping a single-phase smart meter for a three-phase one may mean losing some or all of the smart services the supplier currently provides.
The operator pages checked for this guide publish no standard price for a single-phase to three-phase upgrade, so the quote for your site is the figure to plan around. The guide to new and upgraded business connections covers quotation, timescales and how connection charges are worked out. If chargers are driving the upgrade, the EV charging guide shows how socket numbers and load management change what the supply must carry, and you can send an enquiry through the form on this page.
Sources
- legislation.gov.uk, The Electricity Safety, Quality and Continuity Regulations 2002, regulation 27; checked 28 October 2026.
- UK Power Networks, connections quotation library: 4.2 Supply characteristics and 4.1.6 Supply disturbances; checked 28 October 2026.
- National Grid Electricity Distribution: Fuse upgrade, Homes and small businesses, Commercial EV connections, G98 connection procedures and Assessment and Testing of Alternative Cut-outs; checked 28 October 2026.
- Electricity North West: Three phase power connection, Upgrade or reduce your supply and Smart meter; checked 28 October 2026.
- Northern Powergrid: Small connections, Get connected and Modify a connection; checked 28 October 2026.
Guides on this topic
- DNO Heat Maps and Network Capacity: Checking Headroom Before a Site Adds Load
- kVA to kW Calculator for Business Supplies and Generators
Common questions
Is a larger fuse an alternative to three-phase?
Sometimes. NGED offers to replace older 30 or 60 amp fuses with an 80 amp fuse, and ENWL says a supply above 20kW may need either an amp increase or a change to three-phase. If the planned load would still exceed what one phase can carry, three-phase is the next step.
Will moving to three-phase affect my smart meter?
It can. ENWL says the supplier has to replace a single-phase smart meter with a three-phase meter, and that this may mean losing some or all of the smart services the supplier provides. Ask your supplier what it can offer before the network operator books the work.
Can the network operator change the phases on my supply?
Not on its own. Regulation 27 of the ESQCR says the number and rotation of phases in a supply shall not be varied by the distributor except with the consumer's agreement or, without it, the consent of the Secretary of State. Rotation matters because it sets the direction a three-phase motor turns.
What voltage range should a machine supplier design for?
UK Power Networks gives its low voltage supply as 230/400 volts, +10% and -6%, which matches the limits in the ESQCR. That works out at roughly 216 V to 253 V from phase to neutral and 376 V to 440 V between phases. Give the supplier those figures together with the number of phases.
Does a three-phase supply mean CT metering?
Not necessarily. Northern Powergrid says its small connections, which include three-phase supplies of up to 69kVA, are normally whole current metered, while non-domestic connections above 69kVA are normally CT metered. Your meter and bill show which type you have.