Want to cut what your site uses and pays for energy?
Request a quoteWhat should you check before buying anything?
Measure the voltage the site actually receives. Voltage optimisation lowers the supply to a site's equipment, so it can only help where the supply starts high. Regulation 27 of the Electricity Safety, Quality and Continuity Regulations 2002 sets the declared voltage for a low-voltage supply at 230 volts between phase and neutral, unless the parties agree otherwise in writing. It allows a variation of up to 10 per cent above or 6 per cent below, which works out at 216.2 to 253 volts. For a high-voltage supply below 132,000 volts the allowance is 6 per cent either way.
A site that sits in the middle or lower part of that window has little room for a unit to take voltage down. A high reading is what opens the case. One spot reading will not settle it, because the Energy Networks Association (ENA) notes that voltage cannot stay perfectly still as demand changes over the day. Have a competent electrician fit a logger at the incomer and run it for several weeks, including weekends, so that you see the highs and lows.
If the logger shows the supply outside the permitted limits, there is a different route. Regulation 13 of the Electricity (Standards of Performance) Regulations 2015 applies when a customer tells its distributor that it believes the supply is outside the permitted variations. Where the distributor cannot explain the likely cause without a visit, it must offer one in the time the regulations prescribe or pay the customer a prescribed sum. Otherwise it must send an explanation in the prescribed time. The network operator guide shows who to contact.
One more point on timing. Network operators have proposed lowering the bottom of the statutory range from 216 volts to 207 volts, and ENA says the change would reduce overall network voltage levels. That is a proposal under review, not a rule. If it went ahead, a unit chosen on today's readings could have less to take off, which is a reason to size from recent logs and to ask any supplier how the quote copes with a lower supply.
How does voltage optimisation work?
Business Energy Scotland puts it simply: the unit reduces the voltage applied to electrical equipment. It explains that the grid supplies electricity at a slightly higher level than most equipment needs, to allow for voltage drops over long distances and varying loads. A single device can serve everything on the same supply, and the unit is usually installed beside the fuse board. It lists reduced electricity consumption, lower bills and lower emissions as the intended result. Whether a given site gets them depends on its voltage and its loads.
Which sites and loads are likely to save?
The guide gives a plain split between sites where the measure tends to work and sites where it does not.
| Site type | Business Energy Scotland's view |
|---|---|
| Farms, commercial kitchens and laundry, manufacturing with long-running machinery | Tends to work well where equipment runs continuously or is sensitive to voltage levels. It names compressors, refrigeration units and lighting as voltage-dependent equipment |
| Offices and data centres with modern computing equipment | May be less effective |
| Retail with low energy demand, LED lighting and efficient appliances | May be less effective |
| Sites with on-site generation or battery storage | May be less effective, because voltage is already managed internally |
None of the official or standards-body pages checked breaks savings down by individual load or gives a result for a single type of equipment. That is the reason to measure rather than assume. It also means lighting comes first: a site that has just fitted LEDs has removed some of the load a unit would have acted on. The guide to cutting business energy costs puts voltage checks after controls and lighting for that reason.
What are the limits and risks?
- Equipment tolerance. Business Energy Scotland says a site survey should measure voltage across the premises and assess older or sensitive equipment to ensure it can operate at the lower voltage.
- Visible effects. It says that in rare cases lights may be slightly dimmer or fans slower, though usually negligibly.
- Not a substitute. The same guide says voltage optimisation complements energy-efficiency upgrades but does not replace them.
- A different question. Reactive power and power factor are separate from supply voltage; the power factor guide covers them.
What does it cost, and what do savings claims rest on?
Business Energy Scotland says costs vary with the size of the business and its electricity demand, and it recommends more than one site survey and quote. It publishes no dated price, so compare quotes on the estimated saving and payback each one states.
On savings, the same guide attributes its headline figure to BEAMA, the manufacturers' association. This article repeats no savings percentage. None of the official or standards-body pages checked publishes an independent trial result, and the outcome depends on the site's voltage and load.
How do you test a savings claim?
- Start with your own log. Ask what voltage the unit will deliver and compare that with your measured range.
- Ask which loads the saving relies on and for their running hours, then check them against your metered use. The monitoring guide shows what to measure.
- Ask how the saving will be measured. BS EN 17267 describes a measurement and monitoring plan that accounts for influencing factors and supports verification of savings, and BSI lists ISO 50015 as the standard on measurement and verification of energy performance. A fair test fixes a baseline period and adjusts for weather and output.
- Ask whether the unit can be switched in and out, so that like-for-like periods can be compared.
- Get at least two quotes that state estimated savings and payback, as Business Energy Scotland advises.
Readers who want help placing voltage checks within a wider plan for a site can send an enquiry through the form on the energy management page.
When is it not worth doing?
- The log shows the supply already sits in the lower part of the permitted range.
- The load is mostly IT, LED lighting or other electronics with their own regulation.
- The site has on-site generation or storage managing its own voltage.
- Controls, lighting and obvious waste have not yet been dealt with, which the energy management page treats as the first step.
Sources and last checked
Checked on 22 October 2026. The statutory limits and the network operators' proposal can change, so the legislation and the Energy Networks Association pages are the authority if they disagree with this one.
- legislation.gov.uk, Electricity Safety, Quality and Continuity Regulations 2002, regulation 27
- legislation.gov.uk, Electricity (Standards of Performance) Regulations 2015, regulation 13
- Energy Networks Association, Statutory Voltage Limits
- Business Energy Scotland, Voltage optimisation, a quick guide (undated)
- BSI, BS EN 17267:2019 (30 September 2019) and ISO 50015:2014 (11 December 2014) catalogue pages
Common questions
How much does a voltage optimiser cost?
It depends on the size of the business and its electricity demand, according to Business Energy Scotland, which recommends more than one site survey and quote. No dated official price is published. Ask each quote to state the estimated saving and payback so you can compare them.
Can I ask my network operator to lower the voltage?
If the supply is outside the permitted variations, regulation 13 of the Standards of Performance Regulations gives a customer a route to have the distributor investigate. If the voltage is high but inside the limits, the pages checked give no such duty. Network operators have also proposed lowering the bottom limit, which would reduce overall network voltage.
Does voltage optimisation work with solar panels or a battery?
Business Energy Scotland lists businesses with on-site generation or battery storage among those for which the measure may be less effective, because voltage is already managed internally. A site with either should log its voltage with the system running before considering a unit.
Is there funding for voltage optimisation?
Business Energy Scotland says voltage optimisation is eligible for funding through its SME Loan Scheme. That is a Scottish scheme. Elsewhere in the UK, ask the local business support body or combined authority what is open, and check eligibility before ordering.