Heat Network Zoning in England: Which Towns, Which Buildings and When
Updated 23 October 2026 · Renewable Energy for Businesses
Weighing up a heat pump or other low-carbon heating?
Request a quoteAsk about your site
Heat network zoning is a planned system in England under which local bodies would designate zones where a district heat network is expected to be the lowest-cost low-carbon heat, and certain buildings inside a zone could be required to connect. It is not yet in force. For a business, the test the government has confirmed is simple: a building with a wet heating system and measured annual average heat demand above 100 MWh could be asked to connect once a zone exists and a developer has consent to build the network. Ofgem's separate regulation of existing networks is in the heat network regulation guide.
Is heat network zoning in force?
No. The Energy Act 2023 gives the government powers to introduce zoning in England through regulations. DESNZ published its response to the 2023 consultation on 21 January 2026 after 156 replies, and its summary says the implementing regulations were in development and expected to be laid in Parliament in spring 2026, subject to parliamentary time. Gov.uk's zoning page still describes the first zones as being progressed ahead of the legislation coming into force.
The response sets out the structure. A heat network zoning authority, housed in DESNZ at first and later in the Warm Homes Agency, coordinates zoning nationally. Local zone coordination bodies, which can be led by councils or a combined authority, consult on a proposed boundary, designate the zone and run a competitive process to appoint a zone developer with exclusive rights to build the network. The aim in the Warm Homes Plan is to more than double the heat demand met by heat networks in England to 7% by 2035.
Which towns and cities were in the zoning pilot?
The pilot tested the method in 28 places, and gov.uk lists them as: Barking & Dagenham (see London), Birmingham, Bridlington, Bristol, Canterbury, Carlisle, Cheltenham, Coventry, Darlington, Exeter, Greater Manchester Combined Authority (see Manchester), Hull, Lancaster, Leeds, Leicester, Liverpool, Newcastle, Northallerton, Norwich, Nottingham, Peterborough, Plymouth, Sheffield, Southampton, Southwark (see London), Stoke (see Stoke-on-Trent), Strood and Sunderland.
Being on the list does not make a place a zone. The pilot maps and opportunity reports were produced before the policy was settled, and gov.uk says they should not be relied on for business decisions. A smaller group is further ahead through the Advanced Zoning Programme. DESNZ's market webinars have spotlighted projects in Leeds, Plymouth, Stockport, Bristol, Sheffield, Trafford, Bolton, London and Liverpool. The response also says at least 10 of the biggest English towns and cities will be supported to set up zones soon after the regulations go live.
Which buildings could be required to connect?
| Building | Could be asked to connect? | Detail from the January 2026 response |
|---|---|---|
| New building | Yes | Any building that receives planning permission after the zone is designated |
| Existing communally heated building, domestic or non-domestic | Yes | All are in scope |
| Existing non-domestic building | Yes, above a threshold | Measured annual average heat demand above 100 MWh and a wet heating system |
| Building with an energy centre supplying a campus network | Intended | DESNZ intends to extend the requirement to these buildings |
| Crown-owned buildings | No | The zoning powers do not apply to bodies with Crown status |
DESNZ glosses a wet system as one that is not exclusively heated through electric radiators. Where measured data is not available, demand is estimated from benchmarks for the building's use type. An owner who thinks a building has been misclassified on wrong data can apply to correct it during the exemption window. The same powers cover third-party heat sources such as data centres, water treatment centres and waste incinerators, which can be required to connect if no commercial deal is reached.
What happens after a connection notice, and what can an owner do?
- Timing. The zone developer asks the zone coordination body to issue a connection notice, which it must do within two weeks, and only once the developer has consent to develop. The owner then has 6 months to agree an exact connection date or apply for a temporary exemption, and the connection window must be at least 12 months long.
- Conditional exemptions can cover a building with an existing low-carbon heating system whose expected lifespan is greater than 2 years, binding legal or contractual terms such as lease terms, physical or technical incompatibility such as a direct electric heating system, building safety remediation and conservation requirements such as listed status.
- Temporary exemptions last at most 2 years from the end of the connection window, for example where a low-carbon system reaches end of life soon after, or works would block connection.
- Choice of supply. A connected building may choose whether to buy heat from the network, and can keep its existing heating system while staying connected.
- Cost. DESNZ says it does not yet have the powers to let a developer charge for connecting a building that has received a notice, and expects few notices until that is fixed. It intends to cap non-domestic connection costs against an appropriate counterfactual.
- Penalties. A zone coordination body can issue compliance notices and, for serious or continuing breaches, a variable penalty of up to £1 million or 10% of annual turnover, whichever is higher.
What should a business in a likely zone do now?
- Work out annual heat use in MWh from gas, oil or LPG records. The MPAN and MPRN guide explains where gas consumption appears on a bill.
- Note whether the heating is a wet system, and the age and expected life of the plant. DESNZ says guidance will set expected lifetimes for different technologies and that owners must declare and evidence an installation date.
- Read the lease and any covenants, because contractual restrictions are an exemption ground.
- Ask the council whether the site is in a pilot or early zone area, and watch for the public consultation on a proposed boundary.
- If the site gives off waste heat, say from process cooling or a data hall, note that it may be asked to supply a network.
Where a connection is unlikely or not wanted, on-site options remain. The renewable heating comparison and the commercial heat pump page cover them, and readers can send an enquiry through the form on this page. Metering rules for existing communal systems are in the communal heating guide.
How do the rules differ in Scotland?
Zoning in England is a different regime. In Scotland the Heat Networks (Scotland) Act 2021 already provides for local authorities to designate heat network zones, and 2023 regulations require building assessment reports, with non-domestic buildings below 73 MWh of annual heat demand exempt.
Sources and last checked
- DESNZ, GOV.UK, checked 22 October 2026: heat network zoning collection, Heat Networks Zoning Pilot (updated 25 November 2025), market engagement webinars, the consultation outcome page, the summary of the government response and the full response.
- Legislation.gov.uk, checked 22 October 2026: Heat Networks (Heat Network Zones and Building Assessment Reports) (Scotland) Regulations 2023, explanatory note.
Guides on this topic
Common questions
Will my town become a heat network zone?
Not automatically. Zone coordination bodies designate zones after consulting locally, and DESNZ says it will support at least 10 of the biggest English towns and cities soon after the regulations go live. Gov.uk says the pilot maps should not be relied on for business decisions, so the council is the place to ask.
Does a connection notice mean the business has to buy heat?
No. DESNZ says a building that has received a connection notice may choose whether to buy heat from the network after it connects, and may keep its existing heating system while staying connected. That choice is meant to keep pressure on developers to price competitively.
How is the 100 MWh threshold measured, and what if it is wrong?
The test uses measured annual average heat demand, and where measured data is not available it is estimated from benchmarks for the building's use type. An owner who thinks a building has been classified as required to connect on incorrect data or assumptions can apply to the zone coordination body to correct it.
Does an existing heat pump or boiler affect whether a building can be exempt?
It can. A conditional exemption is available where the building has an existing low-carbon heating system with an expected lifespan greater than 2 years. DESNZ says guidance will set expected lifetimes for different technologies and that owners must declare and evidence the installation date.