Heat Network Regulation in 2026: What Ofgem's Rules Mean for Businesses
Updated 23 October 2026 · Renewable Energy for Businesses
Want to cut what your site uses and pays for energy?
Request a quoteOfgem has regulated heat networks in Great Britain since 27 January 2026, and the duties fall on the operators and suppliers of a network rather than on the people who buy heat from it. A business that runs communal or district heating, or passes heat on to tenants, needs to work out which role it holds and register by 26 January 2027. A business that only buys heat is a customer, and its protections depend partly on its size. Zoning is in the heat network zoning guide and metering and billing in the communal heating guide.
What changed on 27 January 2026?
The Heat Networks (Market Framework) (Great Britain) Regulations 2025 bring most of their provisions into force on 27 January 2026, which they call the launch date. Ofgem's blog describes it as the day new consumer protection rules were formally launched so that Ofgem could begin regulating. Networks already operating did not have to stop and apply first: Ofgem says they were automatically authorised to keep supplying, which it calls deemed authorisation, and it has published rules for operators and suppliers called authorisation conditions.
| Item | Position on 22 October 2026 |
|---|---|
| Ofgem regulation of operators and suppliers | In force since 27 January 2026 |
| Registration with Ofgem | Required by 26 January 2027 |
| Technical standards (HNTAS) | Planned launch in 2027 |
| Heat network zoning in England | Not in force |
Which networks are in scope, and is a business the operator or supplier?
Ofgem defines a heat network as one that provides heating, cooling and hot water to more than one property in a building, or to more than one building, from a central source. It brings five types within the regulations:
- District networks supplying 2 or more buildings, and communal networks supplying a single building divided into separate premises.
- Self-supply networks, where an organisation supplies only itself. Ofgem's examples include hospitals, education campuses and prisons. An organisation that also supplies third parties cannot use this route.
- Industrial networks supplying an industrial site, mainly for an industrial process.
- Shared ground loop networks, with a heat pump for each customer.
Self-supply and industrial networks have fewer obligations than the others. Out of scope are, for example, single buildings with shared facilities that are not divided into separate premises, such as care homes, and communal systems that give heating and any cooling only through air conditioning and no hot water.
The two roles are separate, and one organisation can hold both. The operator controls and maintains the network, and Ofgem says that responsibility stays with it even where contractors do the day-to-day work. The supplier holds the contractual and customer-facing side, including billing and complaints. The explanatory note to the regulations confirms that supplying heat to businesses counts.
For example, the owner of a multi-let office building heated from one plant room, who bills tenants for the heat, fits Ofgem's wording of a communal heat network. Whether that owner is operator, supplier or both depends on who controls the plant and who holds the contracts with occupiers, so Ofgem tells every party to assess its activities against the definitions. A landlord who is also the supplier is subject to both the authorisation conditions and housing legislation. The commercial landlord guide covers the wider landlord position.
What must an operator or supplier do, and by when?
Operators and suppliers of relevant heat networks must give Ofgem details of their organisation, ownership, financial resilience and consumer protection arrangements by 26 January 2027. Ofgem's preparation pages set out the order of work:
- Decide whether the organisation is operator, supplier or both for each network.
- Nominate a regulatory contact, typically the most senior person responsible for heat networks, who creates the digital service account through a GOV.UK One Login.
- Complete a fit and proper declaration for everybody with significant managerial responsibility or influence over heat networks.
- Register the organisation and each network. An operator that is not the supplier starts the process and invites its supplier to register the supply side.
- If the role includes supply, also register with the Energy Ombudsman's heat network supplier scheme.
Registration is the start of the duty. Afterwards an operator or supplier must follow the authorisation conditions, provide data on an ongoing basis and report material changes, such as adding or removing connected buildings.
Ofgem has said it will work collaboratively with the sector in the first year and apply enforcement when it is proportionate. That is a statement of approach, not an exemption. The regulations cap the penalty for a contravention. The cap is the higher of 10% of the authorised person's turnover and £1 million. Carrying on a regulated activity without authorisation is also an offence.
What protections does a business that buys heat get?
Ofgem's consumer protection guidance is aimed mostly at domestic customers, though it includes some guidance on non-domestic requirements. Three points matter to a business customer.
- Redress. Every authorised person must belong to a redress scheme, and the Energy Ombudsman is the one designated. The requirement covers complaints about supply for domestic purposes or for a micro-business or small business only, so a larger business should read its supply contract closely.
- Deemed contracts. Where premises are supplied without agreed terms, the supplier is deemed to have made a contract with the occupier, with charges no higher than under its standard variable supply contract.
- Charges. Where a condition forbids disproportionate charges, Ofgem may specify how to test for them.
| Size | Definition used for the redress requirement |
|---|---|
| Micro-business | Under 247,000 kWh of heat a year, or fewer than 10 full-time equivalent employees and turnover or balance sheet total of £2 million or less |
| Small business | Not micro, and under 420,000 kWh of heat a year, or fewer than 50 full-time equivalent employees and turnover of £6.5 million or less or balance sheet total of £5 million or less |
Ofgem's June 2026 research on 28 interviews with businesses on heat networks, across 26 sites, found limited understanding of heat networks, costs generally seen as affordable compared with gas boilers, and some confusing bills. It is a small sample.
Where do technical standards, zoning and metering fit?
The Heat Network Technical Assurance Scheme (HNTAS) is planned to launch in 2027, phased in over time. DESNZ consulted from 21 January to 15 April 2026 and is analysing responses. These points are proposals in the consultation, not law:
- a mandatory regime for new networks and the roughly 12,000 existing networks in Great Britain;
- no network below six properties, or the capacity equivalent, would be covered. For non-domestic or mixed networks the document uses 450 kW of connection capacity for existing networks and 225 kW for new ones;
- industrial heat networks excluded at launch, with a review later.
The draft technical standard, TS1, builds on the CIBSE CP1 code of practice, and the final version is due before HNTAS launches. The HNTAS guide covers who the scheme is planned to apply to and how operators can prepare.
Zoning is an England-only policy outside Ofgem's regulation. DESNZ's January 2026 summary said its regulations were expected to be laid in Parliament in spring 2026, subject to parliamentary time, and they are not in force. Metering and billing duties come from separate 2014 regulations, which the January 2026 amendments trimmed. In Scotland, Ofgem is also the licensing authority under the Heat Networks (Scotland) Act 2021.
What should a business do now?
- Owners of communal or district heating: list each network, decide the operator and supplier roles, and name a regulatory contact well before 26 January 2027.
- Self-supplying campuses and industrial sites: check whether the network is in scope and which lighter obligations apply.
- Businesses that buy heat: identify the supplier, check the contract for charges and the complaints route, and note whether the business counts as micro or small.
- Businesses weighing options: compare a network connection with on-site heating in the renewable heating comparison. The commercial heat pump page covers the on-site alternative, and readers can send an enquiry through the form on this page.
Sources and last checked
- Ofgem, checked 22 October 2026: Heat networks, who should register, preparing for registration, after registration, blog of 6 January 2026, consumer protection guidance and non-domestic consumer views (25 June 2026).
- Legislation.gov.uk, checked 22 October 2026: the 2025 Regulations and explanatory note, the 2026 amendments and note, and the No. 2 amendments.
- DESNZ, GOV.UK, checked 22 October 2026: HNTAS, the consultation, its document the zoning collection and the zoning response summary.
Guides on this topic
- What Is a Heat Network? District and Communal Heating Explained for Businesses
- HNTAS Explained: The Heat Network Technical Assurance Scheme for Building Owners
Common questions
Does a business that only buys heat have to register with Ofgem?
No. Ofgem puts the registration duty on operators and suppliers of relevant heat networks, not on customers. A business that passes heat on to tenants or other occupiers may count as a supplier or operator, so it should check its own arrangements against Ofgem's definitions.
Is one heat pump or boiler serving a single business a heat network?
Not on Ofgem's description, which is heat to more than one property in a building, or to more than one building, from a central source. Plant that serves one occupier is outside that wording.
What if a network starts after the registration deadline?
The regulations treat anyone already carrying on a regulated activity before the end of the first part of the initial period as authorised. That period ends on the day before the first anniversary of the launch date, 26 January 2027. A network starting later should expect to need authorisation by application, because regulated activity is prohibited without it.
Will the new rules change what a business pays for heat?
Ofgem lists fair pricing among its priorities and may specify how to test whether charges are disproportionate, but neither sets a price. Charges still follow the supply contract, apart from the cap on deemed-contract charges.