Generator Changeover Switches and Automatic Transfer Switches for Business Premises
Updated 24 November 2026 · Renewable Energy for Businesses
Looking at battery storage or backup power for your site?
Request a quoteWhat does a generator changeover switch do?
It decides which source feeds the site. In normal running the load is on the mains; when the mains fails, the switch disconnects it and connects the generator, then reverses the move when the supply is restored. BS EN IEC 60947-6-1:2026, the product standard for this equipment, describes it as being used to ensure continuity of supply by transferring a load between power supply sources.
The switch sits on the site's side of the meter, between the incoming supply and the board, or boards, it keeps alive: the main board, so the set carries everything, or a separate board for essential circuits. The network operator's cut-out upstream is not part of the job. National Grid Electricity Distribution describes the cut-out as belonging to the network operator and forming the interface with the meter operator, and only the network operator may replace its fuse. An ATS panel is the enclosure that houses an automatic switch and the controller that runs it.
Manual or automatic: which suits a business site?
The standard covers switches operated manually, remotely and automatically. The choice turns on how long the site can be without power and whether someone will be there to act.
| Type | How the transfer happens | Suits | Watch for |
|---|---|---|---|
| Manual | A person starts the set, moves the switch from mains to generator, and moves it back when the supply is restored | Staffed sites that can stop for a while, such as workshops and offices | Out-of-hours cuts, and a written start-up and switch-back procedure |
| Remote | The switch is moved by a signal from a control system or a button elsewhere on site | Sites with a building management system or a staffed control room | Who may operate it, and what happens if the signal fails |
| Automatic (ATS) | A controller detects the loss of mains, starts the set and transfers the load, then transfers back once the mains is stable | Unstaffed sites and loads that cannot wait, such as cold rooms, pumps and security | The delay settings, the order in which loads come back, and regular tests |
What happens in the seconds after a power cut?
- The mains fails, and everything on the switched board stops unless a UPS is holding it.
- The controller confirms the supply has gone, after the delay the electrician has set.
- The set starts and runs up to its rated voltage and frequency.
- The switch opens the mains side and closes onto the generator, and the load comes back on.
- When the mains is back and stable, the switch transfers the load back and the set shuts down.
Steps 1 to 4 are a break in supply, and a switch that breaks before it makes gives a second, brief break on the switch back to mains. Equipment that cannot take a break, such as servers, tills and controls, needs a UPS to hold it; the backup power guide covers where a UPS fits alongside a set.
Why must a standby set not run in parallel with the grid?
Because the law requires it of a switched alternative. Regulation 21 of the Electricity Safety, Quality and Continuity Regulations 2002 requires anyone who operates a source of energy as a switched alternative to a distributor's network to ensure it cannot operate in parallel with that network. Where the source is part of a low voltage installation, that installation must also comply with the British Standard Requirements, which the regulations define as BS 7671.
In switch terms, the generator side cannot close until the mains side is open, and the mains side cannot close until the generator side is open. Parallel running is a separate legal position: regulation 22 bars anyone from installing or operating a source that may be connected in parallel unless they have the equipment, people and procedures to prevent danger or interference with the network, meet BS 7671 for a low voltage installation, and have agreed specific requirements with the network operator.
That matters when choosing an automatic switch. The standard includes automatic switches with closed transition capability, which make the new connection before breaking the old one so the load moves without a break. For that moment the set is in parallel with the network, so regulation 22 applies rather than regulation 21. If a supplier offers a no-break transfer, ask what has been agreed with the network operator before anything is wired.
When does the network operator need to know?
It depends on whether the set can ever run in parallel:
- Never in parallel. Regulation 21 places its duties on whoever operates the set and sets no notice step of its own. Whether your network operator wants to hear about such a set is its call, so ask before commissioning.
- In parallel, small. A source producing no more than 16 amperes per phase at low voltage is spared the agreement step, provided it disconnects itself when the network supply is cut off and the network operator is told of the plan to run it in parallel before, or at the time of, commissioning.
- In parallel, larger. Specific requirements must be agreed with the network operator first. Electricity North West says G99 applies to all generation installations over 16 amps per phase, and SSEN asks for at least 15 days' notice before generation equipment above 50 kW is installed and commissioned, because its team attends the test.
A set bought only to stand by, behind a switch that cannot parallel, stays in the first group; the standby generators page covers choosing one.
How is the switch tested, and how do test hours count?
By cutting the mains on purpose. Electricity North West suggests an annual power cut test, simulated by switching off the mains under controlled conditions so that everyone knows the procedure. It exercises the switch, its controller and the set in the order a real cut would, and the generator servicing guide explains how it fits with on-load and load bank testing.
In England and Wales, every test run counts towards the testing limit for an emergency-only set:
- a cap of 50 test hours a year on each backup generator, which only the regulator can raise, and only in writing;
- the regulator can exclude commissioning time within that written agreement;
- the hours tested on each set must be recorded for the year;
- tests should be timed for when background nitrogen oxides are expected to be low, such as outside peak traffic periods.
A transfer test also uses the electricity the set generates on site, which the same guidance asks for. DAERA's guidance for Northern Ireland likewise exempts emergency back-up generators tested for no more than 50 hours a year from its specified generator controls.
Who may install it, and what should you ask the electrician?
A qualified electrician with experience of generator changeover work. Regulation 16 of the Electricity at Work Regulations 1989 bars anyone from work where technical knowledge or experience is needed to prevent danger unless they have it or are suitably supervised. The installation must meet BS 7671, and the switch should be complete equipment: BS EN IEC 60947-6-1 does not cover switch configurations that are not fully type tested by the manufacturer, or marked under the standard, as a complete transfer switch.
Questions to put to the electrician:
- Is the switch type tested and marked to BS EN IEC 60947-6-1 as a complete transfer switch?
- What is its rated current, and how does that compare with the current per phase of the supply or board it switches? The kVA to kW calculator converts a supply's kVA into amps per phase.
- How will it behave under a fault? The standard covers behaviour in abnormal conditions such as a short circuit, so ask which rating applies at this point in the installation.
- Does it break before it makes in both directions, or does it have closed transition capability?
- Does anything it feeds supply safety services such as emergency escape lighting? The standard notes that switches used for those are subject to specific rules and legal requirements.
- How will it be tested at commissioning, and what certification will be issued for the work?
If the set itself is still to be chosen, the page on standby and backup generators covers sizing, fuel, permits and what a supply-and-install quote should list.
Sources
All checked 24 November 2026.
- legislation.gov.uk: Electricity Safety, Quality and Continuity Regulations 2002, regulation 1, regulation 21 and regulation 22; Electricity at Work Regulations 1989, regulation 16; Electricity Safety, Quality and Continuity Regulations (Northern Ireland) 2012, regulation 22.
- BSI Knowledge: BS EN IEC 60947-6-1:2026, transfer switching equipment (published 31 May 2026). National Grid Electricity Distribution: Assessment and testing of alternative cut-outs.
- Environment Agency, Natural Resources Wales, Defra and Welsh Government: Specified generator: when you need a permit (1 September 2022). DAERA: Medium Combustion Plant Directive and Specified Generators (29 June 2023).
- Electricity North West: Business support for power cuts and Generation G99. SSEN: Generation connection at or above 50kW.
Common questions
Is an ATS panel the same thing as an automatic transfer switch?
Usually the panel is the enclosure holding the automatic switch and its controller, ready to connect. BS EN IEC 60947-6-1 covers automatic transfer switching equipment including its controller, and separately covers stand-alone ATS controllers, so check exactly what a quoted panel contains.
Can a hired generator be connected to a business's wiring during a power cut?
Only through a changeover arrangement an electrician has installed for it, so that the set cannot feed back into the network. Regulation 21 applies to any source run as a switched alternative to the network, hired or owned. Electricity North West suggests keeping generator hire among a business's emergency contacts, so settle the connection before a cut rather than during one.
Does Northern Ireland have the same rule against parallel running?
Yes. Regulation 22 of the Electricity Safety, Quality and Continuity Regulations (Northern Ireland) 2012 requires a source run as a switched alternative to the network to be unable to operate in parallel with it, and a low voltage installation that includes one to comply with the British Standard Requirements.
Which standard covers transfer switches?
BS EN IEC 60947-6-1:2026, which BSI Knowledge lists as published on 31 May 2026. It covers manual, remote and automatic transfer switching equipment, bypass/isolation types and automatic switches with closed transition capability, where the rated voltage does not exceed 1,000 V AC or 1,500 V DC.