Standby Generator Maintenance: Servicing Intervals, Load Bank Tests and Fuel Care

Updated 10 November 2026 · Renewable Energy for Businesses

Looking at battery storage or backup power for your site?

Request a quote

Why do standby generators fail when they are needed?

Three causes run through the sources below: a set that is rarely worked hard, fuel that has gone off in the tank, and tests that never prove the set under load.

  • Light loading. Trystar, a US load bank manufacturer, says wet stacking happens when a diesel generator runs under a light load: the engine never gets hot enough, so unburned fuel condenses in the exhaust, and over time the set loses maximum power. An oversized set is prone to it, so check the rating against the real load with the kVA to kW calculator.
  • Fuel. BSI's diesel housekeeping guidance deals with contamination by water, sediment, inorganic contaminants or microbial growth during storage, and Trystar notes that aged diesel degrades and burns less completely.
  • No-load running. Trystar warns that the automatic exercising some sets do is not a load test: it starts the engine without putting it under load.

What does the law say about generator maintenance?

Several duties apply, but none sets an interval:

  • Work equipment. Regulation 5 of the Provision and Use of Work Equipment Regulations 1998 requires an employer to keep work equipment maintained in an efficient state, in efficient working order and in good repair, and to keep any maintenance log up to date.
  • Electrical systems. Regulation 4(2) of the Electricity at Work Regulations 1989 requires systems to be maintained, as far as is necessary to prevent danger and so far as is reasonably practicable.
  • Fire safety. Where the set forms part of the premises' fire precautions, article 17 of the Regulatory Reform (Fire Safety) Order 2005, which covers England and Wales, requires a suitable system of maintenance for it.

HSE's advice is to maintain plant regularly, using the manufacturer's maintenance instructions as a guide, and to use people competent to do the work. For a set supplying safety services, BSI's summary of the standard BS ISO 8528-12 says it applies, for example, to safety equipment in hospitals, high-rise buildings and public gathering places, and sets special requirements for the performance, design and maintenance of those sets.

What goes into a maintenance schedule?

No UK rule fixes these intervals. The manufacturer's schedule for the model comes first; where a figure is given below, it is the US standard NFPA 110 as Trystar summarises it, a published benchmark rather than UK law.

TaskWhat it coversInterval, and who sets it
Routine checksThe checks in the manual, including fluid levelsThe manufacturer's instructions
Test run on loadStarting the set and running it under a real load, not just an automatic exerciseNFPA 110: at least monthly, at 30% or more of the nameplate rating for at least 30 minutes, or at the manufacturer's minimum exhaust temperature for 30 minutes
Load bank testLoading the set with a load bank when the site cannot load it enoughNFPA 110: an annual test where monthly tests cannot be done or are failed, at 50% of nameplate for 30 minutes, then 75% or more for at least an hour
Periodic and annual serviceEngine, alternator and control work in the manufacturer's scheduleThe manufacturer's schedule for that model
Fuel sampling and conditioningTesting stored fuel for water, sediment and microbial growth; polishing or replacing itAgree with the fuel supplier and the servicing firm
RecordsWhat was done, by whom and when, for every test, service and repairEvery visit; the maintenance log must be kept up to date

Trystar adds that NFPA recommends maintenance routines drawn from the manufacturer's recommendations, the instruction manual and NFPA's own minimum requirements.

What does a load bank test do, and when is one needed?

A load bank is an adjustable electrical load: Trystar says its controls let the tester adjust the power drawn from the generator, and describes a load bank test as putting a generator under varying load conditions to see how it reacts. Resistive-reactive banks, Trystar says, provide a 0.80 power factor load so a set can be tested at its rated kVA and power factor, under real-world conditions.

A load bank earns its keep where the site load is too light to work the engine hard. For an engine already showing wet stacking, Trystar's remedy is a few hours at 75% of load capacity, which it says works best for minor cases; an engine with serious build-up needs a thorough evaluation first, because the deposits can ignite.

Some tests should also start from a simulated mains failure, so the transfer switch, controls and set are proved together as a system. Testing hours for emergency-only generators are limited in England and Wales, as the backup power guide explains, so plan the test programme within that limit.

How do you keep stored fuel usable?

  • Test it. Have samples checked for water, sediment and microbial growth, the contamination BSI's diesel housekeeping guidance covers.
  • Clean it. Trystar says fuel polishers treat the diesel in a generator's storage tank to remove sludge, water and other contaminants.
  • Store it properly. The oil storage and bund rules are in the backup power guide.
  • Check the fuel type. The HVO guide covers what to confirm before a set switches to HVO. Whether a set may burn red diesel depends on HMRC's tests, set out in the red diesel guide; Budget 2026 announced that the further temporary cut to rebated fuel duty rates, including red diesel, will run until 30 June 2027 (HMRC, updated 5 November 2026).

What should a servicing contract cover?

Put the scope in writing:

  • Scope: engine, alternator, controls, starting system, transfer switch and fuel system, by make and model.
  • Visits: how often, tied to the manufacturer's schedule.
  • Parts: what is included and what is charged extra.
  • Load testing: how the set will be loaded at each test, and who supplies the load bank.
  • Fuel: sampling, laboratory testing and polishing.
  • Reports: what was done, by whom and when, with defects and readings, so the maintenance log stays current.

Questions to ask a servicing firm:

  1. Which manufacturer's schedule will you follow for this model, and can we see it?
  2. How will you load the set at each test, and to what percentage of its rating?
  3. Will you test the transfer switch under a simulated mains failure?
  4. How will you sample the fuel, and what will the laboratory test for?
  5. Who will do the work, and what training do they have on this make?
  6. What will the report show, and how soon after the visit will we get it?

If a set keeps failing its load tests, weigh repair against replacement, or against pairing it with storage. A UPS, which BSI describes as having a primary function to ensure continuity of load power, can hold critical loads while the set starts and takes over, and a battery can cover short cuts so the generator runs less. The battery storage page covers how such systems are sized and assessed.

Sources

All checked 10 November 2026.

Common questions

How often should a standby generator be serviced?

No UK rule sets one interval. Follow the manufacturer's schedule for the model, which HSE says should guide maintenance, and the site's own risk assessment. For a set supplying safety services, BS ISO 8528-12 sets special maintenance requirements.

What is the 30% rule for generators?

It comes from the US standard NFPA 110, which Trystar summarises as monthly tests at no less than 30% of the nameplate rating for at least 30 minutes, or at the manufacturer's minimum exhaust temperature. Trystar says NFPA dropped lower test loads to cut the chance of wet stacking.

Is running a generator off load bad for it?

An off-load run proves the set starts, but not that it can carry the site. On a diesel set, regular light running can cause wet stacking, so plan on-load tests and, where the site load is too small, a load bank test.

Can we test the generator as often as we like?

Not if it is an emergency-only set in England or Wales, where testing hours are capped; the backup power guide on this site gives the limit and the conditions. Plan load bank tests and monthly runs to fit within it.