NABERS UK and CIBSE TM54: Predicting and Rating an Office's Real Energy Use
Updated 10 November 2026 · Renewable Energy for Businesses
Not sure which technology fits your site?
Request a quoteDesign-stage energy figures and the meter often disagree. TM54 and NABERS UK are two tools UK offices use to close that gap: the first predicts how much energy a building will really use before it is finished, the second rates what an occupied office actually used over a year. This guide explains each, how they compare with other ratings, when a business has to use them, and what they take.
Why do predicted and measured energy use differ?
Because a compliance calculation answers a different question. The Greater London Authority's 'Be Seen' guidance, adopted in September 2021, says Part L calculations give only an indication of a building's theoretical performance, and that a 'performance gap' between design theory and measured reality is well established. Approved Document L itself says the compliance outputs of SBEM and other Building Regulations tools are not suitable as energy forecasts for any size of building. CIBSE's TM54 makes the wider point that energy performance depends on how a building is run and maintained as well as on how it is designed and built.
What is CIBSE TM54?
TM54, Evaluating operational energy use at the design stage, is a CIBSE technical memorandum whose current edition was published in January 2022. It gives building services engineers and energy modellers a method for estimating in-use energy at design stage and for setting performance targets that measured use can later be compared against. CIBSE says it can be applied to any type of building, new or existing.
The difference from a compliance model is scope. TM54 works through operating hours and occupancy, lighting, lifts and escalators, small power, catering, server rooms, hot water, HVAC systems and controls and management factors, then tests the results with sensitivity analysis and scenarios. The GLA describes it as tailoring a Part L model to estimate both regulated and unregulated loads, and says a TM54 analysis gives more accurate predictions of a building's energy use.
It is done during design, by the services engineer or energy modeller, to inform the design, controls and operating strategy, and its results give the first years of metered use something to be measured against.
What is NABERS UK, and who runs it?
NABERS UK rates the energy efficiency of office buildings in England, Wales, Scotland and Northern Ireland on a scale of one to six stars. It is a UK adaptation of the NABERS programme that runs in Australia, and it rates offices only for now. CIBSE was announced as scheme administrator on 2 April 2024, taking over from BRE, and its wholly owned subsidiary CIBSE Certification runs the scheme day to day.
Energy for Offices ratings compare a building's measured energy use with benchmarks built from actual UK office data, taking account of location and occupancy. There are three kinds:
- Base Building: the central services, such as heating and cooling, lifts and lobby lighting.
- Tenancy: what an occupier uses, typically lighting and power plus any special requirements.
- Whole Building: both together, across lettable and common spaces.
A licensed assessor carries out the rating, and a certified rating can generally be promoted for 12 months. New buildings and major refurbishments become eligible as soon as a 12-month rating period can be completed. Ratings can be kept private, although publishing them is encouraged.
Design for Performance is the route for new offices and major refurbishments: the developer or owner signs a Design for Performance Agreement, committing to design, build and commission the building to achieve a specific NABERS UK Energy rating. A member of the Independent Design Review panel reviews the design documentation and energy model, and the GLA describes the target being written into supply-chain contracts and verified after a year of occupation as a measured rating by an independent accredited assessor.
How do TM54 and NABERS UK compare with other building ratings?
The table sets them beside the ratings a business is more likely to know. The BREEAM guide and the Net Zero Carbon Buildings Standard guide cover those schemes in full.
| Tool | What it measures | Design or in use | Required? | Who issues it |
|---|---|---|---|---|
| CIBSE TM54 | Forecast in-use energy, regulated and unregulated | Design | Not by law; named in Approved Document L and asked for in London | The design team's engineer or modeller |
| NABERS UK Energy for Offices | Measured energy over 12 months against UK office benchmarks | In use | Voluntary unless a planning condition requires it | CIBSE Certification, through a licensed assessor |
| NABERS UK Design for Performance | A committed target rating, verified once occupied | Design, then in use | Voluntary; the City of London expects it for major offices | CIBSE Certification, with independent design review |
| BREEAM | Sustainability across many categories, energy among them | Depends on the scheme | Voluntary; some councils set a minimum | BRE |
| EPC | Calculated energy efficiency, A to G | Asset rating | When a building is built, sold or let | Commercial energy assessor |
| DEC | Metered energy over the last 12 months, A to G | In use | Public-authority buildings over 250 m² frequently visited by the public | Accredited energy assessor |
Does a business have to use TM54 or NABERS UK?
Not under any national law, but four sets of rules and standards point to them:
- Approved Document L (England). For new buildings over 1,000 m², the information handed to the owner should include a forecast of actual energy use in kWh a year by fuel, including unregulated loads, and TM54 is one of the methods named. That is in the 2021 edition, in force since 15 June 2022, and carries into the 2026 edition, which takes effect on 24 March 2027 for building work other than higher-risk building work.
- London Plan. Under policy SI 2, the GLA's 'Be Seen' guidance requires major developments to report actual operational energy for at least five years, with a TM54 analysis for non-residential uses above its de minimis threshold. It encourages offices over 5,000 m² to submit a NABERS Energy rating at planning stage, with five stars as best practice for a new multi-let office of that size.
- City of London. The Planning for Sustainability SPD, adopted on 19 February 2025, says major office developments must commit to a minimum NABERS UK base-build rating of five stars for new build or four stars for retrofit where the Development Plan requires it, with Design for Performance registration by RIBA stage 4 at the latest and the rating submitted after the first or second 12-month rating period.
- UK Net Zero Carbon Buildings Standard. CIBSE Journal reported on 30 January 2026 that the voluntary Standard had confirmed offices with a high NABERS UK rating would be 'deemed to satisfy' its operational energy requirements, and CIBSE says this applies in 2026. Version 1 of the Standard, published in March 2026, sets the minimum for a date of commencement from 2026 to 2030 at five stars for new offices and four and a half for existing ones.
What does it take in practice, and what drives the cost?
- Metering by end use and tenant. Approved Document L expects new buildings to submeter so that at least 90% of each fuel's annual use can be assigned to an end use, to monitor each tenant separately, and to allow forecast and in-use energy to be compared. The sub-metering guide covers meter types.
- A full year of data. A NABERS rating rests on 12 months of measured use, so meters need to be reliable before the rating period starts.
- Landlord and tenant working together. The GLA puts base-building services, the HVAC and common parts, on the owner or landlord and lighting and power inside each tenancy on the tenant, so a whole building rating needs both sides' data. The commercial landlords page covers the wider landlord position.
- Weather. NABERS benchmarks allow for location; to track heating between ratings, the degree days guide shows how to separate the weather from real change.
Cost. CIBSE Certification publishes its NABERS UK fees as a download, and its 2026 to 2027 pricing took effect from 1 September. Its pricing page says Design for Performance fees are one-off and the same for whole and base building ratings whatever the size, with reduced charges for tenancies, while Energy for Offices fees are annual and banded at under or over 1,000 m². Fees for the licensed assessor, who is a consultant, and for the design review and energy modelling are separate, and metering upgrades add to the bill. What moves a rating is measured energy falling, which is where the commercial buildings page comes in; readers can send an enquiry through the form there.
Sources
All pages checked 10 November 2026; the scheme and planning pages are the authority if they differ.
- CIBSE: TM54 Evaluating operational energy use at the design stage (January 2022); NABERS UK; NABERS UK partners with CIBSE as new UK scheme administrator (2 April 2024); CIBSE Journal: Net zero standard recognises NABERS (30 January 2026)
- CIBSE Certification: NABERS UK; About NABERS UK; Energy for Offices; Design for Performance; Pricing
- Greater London Authority: 'Be Seen' energy monitoring guidance (September 2021)
- City of London Corporation: Planning for Sustainability SPD (adopted 19 February 2025); Planning guidance
- UK Net Zero Carbon Buildings Standard: FAQs; The Standard, Version 1 Rev 1
- MHCLG and DLUHC, GOV.UK: Approved Document L, Volume 2, 2021 edition incorporating 2023 amendments; Approved Document L, Volume 2, 2026 edition; Energy Performance Certificates for your business premises; A guide to display energy certificates
- BRE: BREEAM
Common questions
Is a TM54 assessment mandatory?
Not nationally. In England, Approved Document L expects new buildings over 1,000 square metres to hand over an energy forecast and names TM54 as one method, and London's 'Be Seen' guidance asks for a TM54 analysis on major non-residential schemes.
How long does a NABERS UK rating last?
CIBSE Certification says a certified Energy for Offices rating can generally be promoted for 12 months, because it reflects the previous year of measured use. It presents annual ratings as the way to show improvement over time.
Can a building that is not an office get a NABERS UK rating?
Not yet. CIBSE Certification says NABERS UK currently rates offices only, although NABERS in Australia also rates buildings such as hotels, shopping centres and data centres.
Who can carry out a NABERS UK rating?
Only a licensed assessor. CIBSE Certification describes licensed assessors as sustainability consultants authorised to conduct NABERS UK ratings, and a Design for Performance project also needs a member of the Independent Design Review panel.