Energy Procurement Strategy: How a Business Decides When and How to Buy Energy
Updated 10 November 2026 · Renewable Energy for Businesses
Not sure which technology fits your site?
Request a quoteWhat goes into an energy procurement strategy?
A short document that the board or budget holder signs off, covering six points:
- The goal. Budget certainty, the lowest average cost over time, a carbon target, or an order of priority between them. Each goal points to different contracts.
- Risk appetite. How far energy costs may move against budget before the business acts. The Government Commercial Agency (GCA), which buys energy for public bodies, offers trading strategies running from short to long term to suit a buyer's appetite for risk; a private business faces the same choice.
- A budget rate. The price per kWh, with network and policy costs included, that the budget assumes, so every purchase can be judged against it.
- Volume and data. Expected kWh by site and month, the half-hourly profile where there is one, and every contract end date.
- Authority to buy. Who can commit the business to a contract or a purchase, up to what value or volume, with whose second signature, and who stands in when a price is about to expire.
- Review and reporting. What is reported, how often, and when the strategy itself is reviewed.
The GCA shows the separation of duties at scale: its in-house team buys in the wholesale market, overseen by a full-time risk team that sets the rules and limits for trading. A smaller business can copy the principle with a named buyer, a second signatory and written limits.
Which buying approaches can a business choose from?
The options run from fixing everything at once to leaving the price to the market. A fixed-rate contract holds the unit rates and standing charges for its full length, so later wholesale moves do not reach the price per kWh. Ofgem describes flexible, or structured, contracts as suitable for big energy users: rather than one locked price, the buyer purchases energy in smaller portions over time. On a variable-rate contract the price can rise or fall during the term as wholesale prices change, and Ofgem notes that some charges can be passed through and added when the supplier knows them. A power purchase agreement buys green electricity directly from a renewable generator over a long term, usually alongside a supply contract for the rest, as the corporate PPA guide explains; the PPA and procurement page compares it with owning generation.
| Buying approach | Budget certainty | Exposure to wholesale moves | Admin effort | Who it suits |
|---|---|---|---|---|
| Fixed for the term, bought at signing | High for the term | All priced on one day, then none until renewal | Low | Small and medium users that want a known budget |
| Flexible, bought in tranches | Builds as each tranche is bought | Spread across many buying dates | High: needs a written policy and someone to act on it | Large users with the data and sign-off to manage it |
| Variable or index-linked | Low | Continuous through the term | Medium: needs monitoring | Buyers who can absorb movement or expect to change contract soon |
| Pass-through lines within a contract | Partial | Limited to the lines passed through | Medium: needs checking against invoices | Any buyer who knows which lines can move |
| Power purchase agreement for part of the volume | High on the covered volume, for years | Low on that volume, but locked in if prices fall | High: a long, specialist contract | Large, creditworthy buyers with steady long-term demand |
| Out-of-contract or deemed rates as a stopgap | None | Full, usually at dearer rates | Low to start, costly to stay on | A short, costed bridge when longer offers look poor |
When should a business start buying?
Well before the switching window, which Ofgem says opens a few months before a fixed contract ends. Staged buying needs far longer: each of the GCA's public sector solutions delivers 12 months of energy after a buying window, so a solution lasting 18, 24, 36 or 42 months starts buying 6 to 30 months before delivery begins. Short windows carry timing risk: the GCA's short-term strategy for winter 2022 was bought over summer 2022, when gas and electricity prices were already high.
Term is a separate choice. Ofgem's March 2026 blog said contract lengths were starting to return to three to five years, and advised asking suppliers what contracts are available and weighing both short and long-term options. For market data, DESNZ publishes what non-domestic users paid each quarter by consumption size band, and the wholesale prices guide lists the official market data worth watching. This guide makes no forecast: a sound strategy is one the business can live with whichever way prices move.
How do you run an energy tender?
- Build the data pack. Every MPAN and MPRN, the site addresses, meter types, contract end dates, a year of consumption and the half-hourly data for half-hourly sites. A non-domestic customer, or a third party it nominates, can ask its supplier for up to a year of historic data from a smart or advanced meter, and suppliers must deal with such requests in 10 working days. Add the credit information bidders will want: suppliers can pick their customers by factors such as supply size or credit rating, and may ask for a security deposit.
- Write the specification. Sites, start date, term, the contract type or buying approach, any green requirement, payment terms, how pass-through charges must be shown, how long bids must stay valid and who will sign.
- Issue the invitation. Send the same pack to each supplier, or to a broker who will approach several, with a deadline and one format for prices.
- Evaluate like for like. Restate every bid as an annual total and an effective price per kWh on the same consumption and dates, then score the terms; the guide to comparing quotes sets out the method line by line.
- Award and sign. Get the final offer in writing, check it against the specification and sign while it is still valid. Business energy contracts carry no cooling-off period.
Public bodies can use a framework instead. The GCA's Supply of Energy 2 agreement (RM6251), which ends on 27 February 2027, has customers sign a Customer Access Agreement authorising the GCA to trade and buy gas and electricity on their behalf, and its replacement, RM6390, offers a choice of trading strategy based on a buyer's level of risk.
Where do brokers, green tariffs and PPAs fit?
Brokers. A broker can run the tender and negotiate, but the supply contract is always with a supplier, and the broker's fee is part of the cost being compared. Under Ofgem's rules, broker costs collected through the supplier appear in the principal terms of business contracts signed from 1 October 2024. The energy brokers guide covers payment, disclosure and checks.
Green procurement. Decide first which claim the business needs to make. A REGO-backed green tariff and a power purchase agreement support different claims, as the REGO and green tariff guide explains. The GCA's framework includes provisions for sleeving PPAs, which it says let public bodies buy green energy directly from renewable generators at prices fixed for the long term; the PPA and procurement page sets out how PPAs compare with other routes for a business.
How should results be governed and reported?
- Cost against budget. The bought and expected price per kWh against the budget rate, monthly or quarterly.
- Share of volume bought. For staged buying, the share of next year's volume already priced, against the limits the strategy sets.
- Market reference. Outturn set against DESNZ's non-domestic prices for the same size band, as a reference rather than a target.
- Exceptions. Any purchase made outside the limits, and who approved it.
- Annual review. The goal, risk appetite, contract mix, end dates and authority levels, re-tested each year and after any large change in use, such as a new site or on-site generation.
The GCA's service includes regular reports on energy prices and their effect on each customer's budget. A business buying on its own needs the same report from its finance team, broker or supplier, and should judge the strategy over several years, not on one renewal.
Sources
All checked 10 November 2026.
- Ofgem: Get a business energy contract; Switch your business energy supplier; Managing business energy costs in an uncertain market (31 March 2026); Third Party Intermediaries: what your microbusiness needs to know (14 October 2022); Ofgem confirms greater protection for businesses (5 April 2024).
- Government Commercial Agency (formerly Crown Commercial Service): RM6251 Supply of Energy 2; RM6390 Supply of Energy and Decarbonisation Services; energy solution tool; public sector energy buying over winter 2022 (10 May 2023, updated 17 May 2023).
- Department for Energy Security and Net Zero (GOV.UK): Gas and electricity prices in the non-domestic sector (updated 29 September 2026); non-domestic smart meter supplier obligations (updated 1 September 2026).
Common questions
Does a small business need an energy procurement strategy?
A short one helps: the contract end dates, the goal, who signs and when buying starts. Ofgem aims flexible contracts at large users, so for a smaller business the strategy is mostly about timing, contract type and term, which a one-page note can record.
Is a longer fixed contract always less risky?
It swaps one risk for another. A long fixed term removes price movement for its length, but leaves the business paying the agreed rate if the market falls, or if it uses less or moves premises. Ofgem's March 2026 blog advised weighing both short and long-term options, so put both to the decision-makers with the reasons.
Who should be allowed to sign an energy contract?
Whoever the strategy names, within written limits: for example, a named buyer who can accept prices up to a set value or volume, with longer or larger commitments going to the finance director or board. Because there is no cooling-off period, the limits need to be agreed before a deadline arrives, not on the day.
How do public bodies buy energy?
They can buy through the Government Commercial Agency, which replaced the Crown Commercial Service on 1 April 2026. Its Supply of Energy 2 agreement (RM6251) runs to 27 February 2027 and is being replaced by RM6390. Customers sign a Customer Access Agreement that authorises the GCA to trade and buy gas and electricity on their behalf.