How Much Does a Commercial Wind Turbine Cost? UK Guide 2026
Updated 20 October 2026 · Renewable Energy for Businesses
Thinking about a wind turbine for your site?
Request a quoteIs wind a fit for your site?
Most business premises are poor sites for wind. A turbine needs a steady wind at hub height, open ground around it and enough distance from neighbours, and the buildings, trees and kerbside clutter of a typical industrial estate or town centre break the wind up. Where a business owns open land, a farm or a large yard on an exposed site, wind can sit alongside solar in a mixed plan; in most other places solar and storage will be the simpler first step. The wind and CHP page covers where on-site generation beyond solar belongs in a business plan.
What drives the cost of a commercial wind turbine
There is no current published national price list for small and medium turbines (the latest named UK table, below, dates from 2012), and the totals depend on the site more than on the machine. Ask every supplier to break a quote into these lines so quotes can be compared like for like:
- The turbine and tower: rated power, rotor diameter and tower height, because output rises with both swept area and hub height.
- Foundations and civil works: ground conditions, access for cranes, cable trenching.
- Grid connection and protection: the distribution network operator's connection offer, metering and the protection equipment it requires.
- Surveys and consent: wind resource assessment, noise, landscape and visual impact, shadow flicker, ecology and any community consultation.
- Running costs: servicing, insurance, inverter or gearbox replacement over the life of the machine, and the land or lease terms.
What does a commercial wind turbine cost per kW?
There is no current public price list, so the best named UK source is RenewableUK's Small and Medium Wind UK Market Report, published in April 2012, which reported fully installed costs from a study by Element Energy. They are 2012 prices and are not uplifted for inflation here, so read the table for its shape, not as a quote: cost per kW falls as turbines get bigger.
| Rated power | Installed cost per kW (2012) | Installed cost (2012) |
|---|---|---|
| 2.5 kW | £6,400 | £16,000 |
| 5 kW | £4,800 | £24,000 |
| 6 kW | £4,000 | £24,000 |
| 11 kW | £4,900 | £54,000 |
| 13 kW | £4,300 | £56,000 |
| 50 kW | £4,200 | £210,000 |
| 100 kW | £3,500 | £350,000 |
| 300 kW | £2,500 | £750,000 |
| 500 kW | £1,900 | £950,000 |
The report says costs per kW are relatively constant up to 50 kW, after which they fall by more than £1,000 per kW, and that the installed cost per kW of a 500 kW machine is 50% lower than for a turbine in the 5 to 15 kW range. It put a 500 kW turbine at £850,000 to £1 million installed; the table shows the mid-point.
For the other end of the scale, the Department for Energy Security and Net Zero's cost review of onshore wind, prepared by Arup and published on 14 July 2025, gives a total capital cost of £1,588 per kW (low £1,241, high £2,205) in 2023 prices, made up of £81 predevelopment, £1,204 construction and £303 infrastructure. Those are developer-survey figures for onshore wind projects in general, not for one commercial turbine, so they show where cost per kW heads as projects grow rather than what a business will be quoted.
A worked example from the 2012 mid-points: a 100 kW turbine at £3,500 per kW is £350,000 installed, against £750,000 for a 300 kW machine at £2,500 per kW. Do not budget from either figure. Ask suppliers for current quotes broken into the lines above, then use the cost-per-kWh method below.
Turn a quote into a cost per kWh
A headline price says little until it is divided by what the turbine will generate. The method is: annual output in kWh = rated power in kW × 8,760 hours × capacity factor; cost per kWh = (the capital cost spread over the machine's life + annual running costs) ÷ annual output. The capacity factor is the share of the year's maximum the turbine delivers, and it is the number that decides the answer. It must come from a wind assessment for your site, for example a first pass from the Global Wind Atlas and then measured data, not from a brochure. Compare the result with what you pay for grid electricity per kWh on your own bill, and with the equivalent calculation for a solar array on the same site.
Planning: when the rules rule it out
Planning is the step that most often stops a commercial wind project. In England, the National Planning Policy Framework (published 17 August 2026; chapter 10, policy W3) says proposals outside the areas a development plan identifies as suitable should be assessed against its national decision-making policies taken as a whole. The older planning practice guidance on renewable and low carbon energy (last updated 14 August 2023) still says a wind application should not be approved unless the site is in an area identified as suitable, so ask the council which wording it applies. The guidance points authorities to ETSU-R-97 for noise, says shadow flicker can only affect properties within 130 degrees either side of north of the turbines at UK latitudes, and requires pre-application consultation for proposals with more than two turbines or a hub height above 15 metres. Microgeneration is often permitted development, but do not assume it for a commercial machine: ask the local planning authority before spending on surveys.
Selling the power and the tax treatment
Ofgem lists wind among the technologies that qualify for the Smart Export Guarantee for installations in Great Britain up to 5 MW; each licensed supplier sets its own export rate. Owned plant is plant and machinery for capital allowances, and in England on-site renewable generation plant is left out of the rateable value under SI 2022/405. Use the funding checker to see which routes fit your organisation and nation, and confirm your own tax position with your adviser.
Questions to put to a supplier
- What wind speed and capacity factor does the quote assume at hub height, and where does that come from?
- Which surveys does the price include, and who carries the risk if planning is refused?
- What is the quote per kWh generated over 20 years, with servicing and replacement parts included?
- What does the grid connection offer say, and has the network operator been approached?
- Is the turbine certified to a recognised small-wind standard, and what warranty covers the gearbox or generator?
Questions people ask
Do I need planning permission for a commercial wind turbine?
Usually yes. Microgeneration is often permitted development, but a commercial turbine normally needs an application, and in England a proposal outside the areas a local plan identifies as suitable is judged against the National Planning Policy Framework (August 2026) as a whole, though older guidance still says it should not be approved there. Scotland, Wales and Northern Ireland have their own rules, so start with your local planning authority.
How much does a commercial wind turbine cost?
There is no official national price list, and installer quotes vary with turbine size, tower height, foundations, grid connection and the surveys planning needs, so this guide gives the method rather than a number. Get written quotes from more than one supplier for your own site, and compare them as a cost per kWh generated, not as a headline price.
Can I sell the electricity from a business wind turbine?
Yes, if it is in Great Britain and within the limit. Ofgem lists wind among the technologies that qualify for the Smart Export Guarantee, up to 5 MW; each licensed supplier sets its own rate per kWh exported.
Sources and last checked
Checked on 20 October 2026. Renewable and low carbon energy, planning practice guidance, gov.uk; Smart Export Guarantee, Ofgem; SI 2022/405, legislation.gov.uk; Global Wind Atlas, DTU. This guide quotes turbine prices only from the two sources named here: Small and Medium Wind UK Market Report, RenewableUK, April 2012 (figure 8 and the table beneath it), and Renewable Energy Generation Cost and Technical Assumptions: Onshore Wind and Solar PV, Cost of Electricity Report Update 2024, Arup for DESNZ, 14 July 2025 (table 3); both read on 9 November 2026. Rules and schemes change; the official pages are the authority if they disagree with this one.